Brisbane battery innovator gets first chunk of funds towards giga-scale production plans

Published by

Brisbane headquartered battery innovator Li-S Energy announced on Tuesday that it has received the first $1.9 million tranche of funding from the Australian Renewable Energy Agency (ARENA) to build a gigawatt-scale factory to produce its lithium-sulfur batteries.

ARENA awarded Li-S Energy $7.86 million in funding in November of last year to undertake manufacturing optimisation, a feasibility study, and front-end engineering design (FEED) for a proposed manufacturing facility to mass produce battery cells.

The proposed factory would be built in stages up to a total production capacity of 1 gigawatt-hour (GWh) per year – 500 times the capacity of Li-S Energy’s current facility, which is based at the Geelong campus of Deakin University in Victoria.

On Tuesday, Li-S Energy confirmed that it had received the first $1.9 million tranche of funding, awarded under ARENA’s Advancing Renewables Program (ARP).

Li-S Energy also confirmed that it had appointed Hatch as engineering consultant to deliver the Phase 4 Front-End Loading (FEL-1) feasibility study for Li-S Energy’s large-scale lithium-sulfur battery manufacturing facility.

The Phase 4 FEL-1 feasibility study will define the early-stage technical, infrastructure, and commercial framework necessary to support a credible manufacturing scale-up pathway beyond Li-S Energy’s existing Phase 3 automated production line in Geelong.  

“We are pleased to have received the first $1.9 million tranche of ARENA funding under the Advancing Renewables Program,” said Dr Lee Finniear, CEO and managing director of Li-S Energy.

“This funding supports the critical engineering work required to progress our Phase 4 manufacturing scale-up pathway toward large-scale production readiness.

“The appointment of Hatch is an important step, bringing demonstrated global battery manufacturing expertise and relevant FEL study execution experience, including work across gigafactory-scale battery projects and lithium-sulfur chemistry.”

Li-S Energy was founded in 2019 through the collaboration of two teams of specialist nanomaterials scientists, one located at Deakin University’s Institute of Frontier Materials, and the other at Brisbane based BNNT Technology.

By embedding nanomaterials, Li-S Energy has developed a 20-layer battery cell using a third-generation (GEN3) semi-solid state lithium sulfur technology, which boasts current energy densities of 456 Wh/kg – around 45 per cent more than competing technologies – and which is also safer and more reliable than lithium-ion batteries.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by
Tags: Li-S Energy

Recent Posts

CEFC names new CEO to lead federal green bank through “decisive decade” of energy transition

The federal government's green bank has named the new CEO, to take the reins at…

23 July 2026

Solar Insiders Podcast: Panel recycling at the precipice

James Petesic from PV Industries on the struggle to stay afloat with the federal PV…

23 July 2026

“A question of trust:” Net zero chief slams state for falling short on targets despite a lot of talk

Net Zero Commission says Australia's biggest state economy is falling well short of targets, despite…

23 July 2026

Regulator suspends 21 companies in crackdown on false statements over solar and battery installs

Regulator says it has suspended 21 companies from the scheme supporting rooftop PV and home…

23 July 2026

Renewable zone to get major boost in mobile and internet coverage as part of benefits package

State government grants to help telcos upgrade mobile and internet black spots as part of…

23 July 2026

Contract awarded for concrete foundations and early works for ten massive spinning machines

Contracts awarded for concrete foundations and other early works for ten huge spinning machines required…

22 July 2026