Biggest solar farm in Queensland connected to the grid

Published by

Neoen Australia’s massive 400MW solar farm in the Queensland Western Downs region has reached a major new milestone, with connection to the electricity grid in the state’s south east now complete.

The solar farm is part of Neoen’s Western Downs Green Power Hub, located 22km south-east of Chinchilla, that will include a 200MW/400MWh big battery, and is expected to produce more than 1,080 GWh per year.

Production is still some way off, with final installations to be completed and a period of testing and commissioning.

Construction of the solar component of the Green Power Hub kicked off in July, 2020 – just as Covid-19 pandemic started to bite in Australia – off the back of a landmark deal with state-owned generator CleanCo to buy 320MW of its output.

The “significant milestone” for the project was marked on Thursday by Queensland energy minister Mick de Brenni, who described the progress of the Hub as a “further proof of Queensland’s credentials as a renewables superpower.”

“This record-breaking project near Chinchilla is backed by government-owned clean energy company, CleanCo, which has committed to purchasing 320MW of the solar power produced,” de Brenni said.

“An economic assessment by Aurecon estimates the project will generate more than $850 million in overall economic activity for Queensland, with 25 per cent expected to be spent in the Western Downs region, helping communities affected by drought and the impacts of COVID-19.”

CleanCo Queensland chair Jacqui Walters said the Western Downs Green Power Hub would join the utility’s unique portfolio of wind, hydro and gas and enable it to offer reliable, low-emissions energy at a competitive price for customers.

“We have a mandate to bring 1,400MW of new renewable energy online by 2025 and through projects like the Western Downs Green Power Hub we will do this while supporting growth and jobs in regional Queensland,” Walters said.

Neoen Australia managing director Louis de Sambucy said the team behind the development of the Hub remained “mobilised towards finalising construction” over coming months.

The goal for the project has been to have the entire Hub built by 2024, with the first power to be delivered in the middle of 2022.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Solar Sharer free power offer is being undermined by higher network charges and complex tariffs

Some households will use batteries, EV charging and behaviour change to make very good use…

3 July 2026

China battery giant launches major new push for “circularity” amid EV and home storage boom

China battery giant launches two major initiatives aimed at improving the sustainability of battery manufacturing,…

3 July 2026

Government-backed community battery rollout is way behind schedule, with only a quarter built on time

A report into the progress of the federal government's Arena-backed community battery rollout has revealed…

3 July 2026

One of Australia’s first solar and battery hybrid projects reaches financial close, confirming big shift in market

One of Australia's first solar and battery hybrid projects reaches financial close, confirming big shift…

3 July 2026

Solar battery rebate expanded to apartments and big energy users for up to 30 MWh in game-changing move

State government quietly reboots its paused solar battery rebate and expands the scheme to offer…

3 July 2026

Australian software allows Italian homes to get free power from solar panels in Spain. Why not here?

Innovative energy trading using Australian software is "going gangbusters" in Europe – and making our…

3 July 2026