Fresh delay to contentious Middle Arm gas project prompts call to “cancel it for good”

Published by

The timeline for developing the Middle Arm gas and petrochemical hub in Darwin Harbour has been pushed back again, prompting a local environmental group to demand the project be cancelled once and for all.

The Northern Territory government has quietly pushed back the deadline for the project’s developers to submit key documents for its environmental approval documents until 7 October 2028, after they missed the deadline for 7 October last week.

The Environment Centre NT said the project was supposed to have been completed by this year, according to its original plan, released in 2021.

It has also been sitting on a potential federal subsidy of $1.9 billion, pledged by the Albanese government, to dredge the Elizabeth River and build industrial jetties at the Middle Arm peninsula, and cover the costs of associated “regional logistics hubs”.

“It’s no surprise the NT government needs a further extension for environmental approvals for Middle Arm – rolling scandals have shown the project would be a disaster for our health, climate, and beautiful Darwin Harbour,” said Bree Ahrens, acting co-executive director of Environment Centre NT.

“There is no shortage of ideas for how the Federal subsidy could be used to enrich the lives of Territorians – but instead it’s chained to a project that would spell disaster for our communities and nature, if it ever happens at all,” Ahrens said.

Renew Economy sought comment from the NT government.

The environmental group said the latest delay followed a decision in February 2024 by Infrastructure Australia to reject the hub’s business case put forward by the NT Government. In late 2024, the NT government extended the original timeframe for environmental approvals for the first time.

In June it was revealed in NT Estimates that $36.2 million of taxpayer money had already been spent on logistics and infrastructure for Middle Arm, the environment group said.

The government has maintained a preference for developing fossil fuels in the territory.

Last month, NT chief minister Lia Finocchiaro oversaw a ceremonial ribbon cutting event to mark the flow of first fossil gas from the Beetaloo Sub-basin, declaring the moment as “a win for all Territorians and a true turning point for the Territory.”

The Environment Centre NT, however, said the Beetaloo event was a “PR stunt” that masked the project’s “bleak economic prospects” and a lack of social licence to proceed. The initial deliveries were merely appraisal gas, and the overall project’s viability remained in doubt, it said.

Peter Hannam is a veteran journalist whose work spans almost four decades and includes stints outside Australia, including time in China, Japan, Singapore and Mongolia. He has lately reported extensively on energy, climate and environmental issues in Australia, and also worked for the federal Climate Change Authority as a special media advisor.

Peter Hannam

Peter Hannam is a veteran journalist whose work spans almost four decades and includes stints outside Australia, including time in China, Japan, Singapore and Mongolia. He has lately reported extensively on energy, climate and environmental issues in Australia, and also worked for the federal Climate Change Authority as a special media advisor.

Share
Published by

Recent Posts

Australia’s top ranked home battery supplier unveils larger all-in-one BESS for commercial and industrial sites

Australia's leading home battery supplier offers bigger all-in-old battery solution for commercial and industrial sites…

27 October 2026

Letting data centres build first, catch up on renewables later could add $40 billion to power bills

Data centres should carry the cost of higher electricity rates if allowed to build now,…

26 October 2026

Well done, Angus: Taylor vows to slash Arena, home battery and EV funding to pay for promised tax cuts

Coalition leader Angus Taylor wants to scrap renewable energy agency, funding for home batteries and…

26 October 2026

Australia enjoys surge in wind, solar and battery projects, with $32.5 billion now financed or under construction

Across Australia, $32.5 billion of generation and storage is now under construction or at financial close,…

26 October 2026

Keep the temperature down: In an anxious world, we need to make the energy transition work for everyone

The response to the shocking attack on Helen Haines suggests we need to bring more…

26 October 2026

The men who fought off Fortescue have a new 4 GW Pilbara wind and solar project in the wings

A new 4 GW wind and solar project is intended to power green iron prospects…

26 October 2026