Big battery added to Aurora solar project could triple its earnings, says report

Published by

Adding battery storage to a 70MW solar plant planned for development near Port Augusta in South Australia would more or less triple the annual revenue of the project, a new report has shown.

The Aurora Project is being planned for construction by South Australia technology company 1414 Degrees after the project was abandoned by US outfit SolarReserve, along with that company’s plans for a 150MW concentrated Solar Tower Project.

1414 Degrees bought the undeveloped project from SolarReserve in late 2019 with the aim of installing a mix of solar PV, battery storage and the ASX-listed company’s unique thermal energy storage system, also known as TESS.

The company said this month it was “pioneering this competitive solution” for the resuscitated Aurora project under the leadership of Marie Pavlik, who was had commissioned modelling from specialist agencies CQ Energy and ITP Renewables and was teaming with energy retailers to bid on power purchase agreements (PPAs).

According to the modelling – a simulation based on the past five years of NEM and FCAS trading – the addition of a 70MWh battery energy storage system to the 70MW plant would generate annual revenues ranging from $44-$80 million, compared to $12.5-$28 million without batteries.

“Although based on historical data that may or may not be a guide to future conditions, these revenue simulations are very encouraging for the development of our Aurora Project,” said 1414 Degrees executive chairman Dr Kevin Moriarty.

“We are working to lock in PPA’s to secure cash flows for the first stage of PV generation to complement the BESS revenue streams.”

The report says a NEM connected solar PV farm with both a BESS (battery energy storage system) and 1414 Degrees’ TESS (thermal energy storage system) will likely fare even better, attracting revenues across wholesale energy, frequency control and ancillary services (FCAS) markets. Modelling on this scenario is in the works.

1414 Degrees’ TESS – the company’s name comes from the very high melting point of silicon, 1414° Celsius – stores energy generated from electricity or gas and supplies both heat and electricity. The energy from the latent heat is recovered as very hot air that powers a turbine to produce heat and electricity when required.

Its plans include using South Australia’s abandoned Aurora Solar Tower Project as a site to pilot its TESS-GRID technology, which the company says could deliver long-duration renewable energy storage services of a similar scale as the dumped concentrated solar project, and on par with pumped hydro.

But those plans hit a major bump in the road last month, after the results of a review of the company’s silicon-based technology found it falling short on key efficiency and reliability metrics, sending the South Australia-based company’s share price down by nearly 40%.

(Just last week, 1414 Degrees’ share price rebounded, jumping from $0.087 on July 15 to a high of $0.22 on July 16, and prompting a “please explain” from the ASX.)

But Moriarty was undaunted by the findings of the review, however, and told RE that the company’s “now highly qualified technical team” was working on fixing the technology’s shortcomings and had mapped out a path to make it competitive in the long-duration energy storage market.

In a statement on July 9, Moriarty said that the addition of the 1414 Degrees’ TESS to the Aurora project would “provide a complete green hybrid solution” for the South Australia grid as renewable penetration increased.

“The Aurora Project can provide robust system strength throughout the NEM because it is situated on major transmission lines, generating revenue stacks from many different services,” he said.

 

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

Sea-surface temperatures at record levels as climate negotiators meet for pre-COP talks in Tuvalu

Leaders and delegates meeting in Fiji and Tuvalu this week for climate negotiations are doing…

6 October 2026

SwitchedOn podcast: Why electricity is now central to the fight against poverty

Global Citizen's Michael Sheldrick on why the global push to electrify could lift millions out…

6 October 2026

Plan to cap wind farm land lease payments sparks controversy, may jeopardise new projects

Controversy has erupted over a planned cap on land lease payments for wind farms in…

6 October 2026

Australia pledges $13 million to help Pacific nations quit diesel, switch to renewables and electrify

Australia dedicates $13 million to help Pacific nations quit fossil fuels, electrify and transition to…

6 October 2026

Australian renewable-powered mine to supply “green gold” for repairs to London’s St Paul’s Cathedral

Australian gold mine, largely powered by renewables and the first in the world to reach…

6 October 2026

Australia’s biggest coal generator set to be replaced by the world’s biggest battery

Origin Energy seeks approval for new addition to its Eraring battery that would take the…

5 October 2026