BHP says two solar farms and big battery to power nickel mines supplying Tesla

Published by

Mining giant BHP has announced plans to build two new solar farms and a battery energy storage system to help power its Nickel West operations in Western Australia’s Goldfields region, and cut its dependence on diesel and gas.

BHP said the Northern Goldfields Solar Project, which it will build in partnership with TransAlta, would include a 27.4MW solar farm at its Mt Keith open pit nickel mine and 10.7MW of solar and a 10.1MW (MWh not specified) battery at the Leinster open pit and underground nickel mine.

The miner said the solar and battery projects, which remain subject to final approvals from the WA government, would be built, owned and operated by TransAlta as part of a power purchase agreement (PPA) extension signed in October 2020.

The project marks the first large-scale onsite solar farm and battery that BHP has commissioned at any of its global operations, the company said on Friday.

The plan for the solar and battery projects follows hot on the heels of a massive deal inked between BHP and Tesla that will see the EV and battery giant source Australian nickel from BHP’s Nickel West operations.

In an announcement last week, as reported on RenewEconomy’s EV-focused sister site The Driven, BHP said its Nickel West operations were among the “most sustainable and lowest carbon emission” producers of nickel around the world.

This week, BHP Nickel West asset president Eddy Haegel said sustainable low carbon nickel was essential for the miner’s battery and electric vehicle customers.

“The Northern Goldfields Solar Project will further improve our position as one of the lowest carbon nickel miners in the world,” Hagel said.

“It will reduce emissions from electricity use at Mt Keith and Leinster by 12 per cent, reduce fuel costs and improve the reliability of our electricity supply with the addition of the battery storage system.”

Company-wide, BHP has a medium-term target to reduce Scope 1 and 2 emissions from its operated assets by at least 30 per cent from 2020 levels by 2030.

Construction of the solar and battery projects will begin in in the first half of 2022 and is expected to take 12-14 months, and at its peak will employ over 100 people on site.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: BHP

Recent Posts

Home battery rebates and soaring diesel costs bring electrification to the masses

What does it take to make a petrol-head tradie home electrification-curious? Try home battery rebates…

1 April 2026

A fair energy system is worth fighting for, but without playing the solar and battery blame game

Claims that solar and battery households are “not paying their way” on the grid –…

1 April 2026

Arena-backed green hydrogen plan disappears from queue for federal environmental approval

Arena-backed project hoping to kickstart a major solar and wind-backed green hydrogen hub has been…

1 April 2026

Oversize and overmass: State allocates $180m to road upgrades to transport huge wind turbine parts

State government tips more than $180 million into road network upgrades to support the transport…

1 April 2026

Electric trucks are increasingly competitive, and could be a thing – if only the transport minister would listen

It is clear that electric trucks are increasingly competitive. Australia has an opportunity to seize…

1 April 2026

Energy Insiders Podcast: Is fuel rationing inevitable?

How did it come to this? Energy security expert and former deputy chief of the…

1 April 2026