Australia’s biggest wind project installs first turbine

Published by

Only days after the mammoth Golden Plains Wind Farm signed its second power purchase agreement (PPA), Australia’s largest wind farm has installed its first 6.2MW turbine.

Under development by Portuguese-based clean energy company TagEnergy, the first phase of the Golden Plains Wind Farm has marked an important milestone with the successful installation of its first Vestas wind turbine.

Measuring 149 metres tall with 79-metre-long blades, the V162 turbine is the first of 122 to be installed at the 756 Golden Plains Wind Farm – East – the first stage of the 1.35 GW project, which will be the biggest in Australia when complete.

It took only six days to erect the turbine following on the heels of three months of critical civil works and laying the foundation. Construction got underway with the turning of the first sod in April 2023 and laying the foundations for the 300MW battery storage facility that will be co-located with the wind farm.

The Vestas V162 6.2MW turbine is the first of its type to be installed in Victoria and has the company’s highest rated output in Australia.

“Seeing the first turbine in place is an incredible moment in the history of this vital project that will deliver clean energy to the grid to accelerate the energy transition,” said Andrew Riggs, TagEnergy managing partner for Australia.

“We trusted in the expertise of our valued partner Vestas, and they delivered an incredibly complex installation safely and on schedule in an impressive six days. We’re excited to see more turbines erected as our project moves ever closer to fruition.”

Earlier this week, TagEnergy signed the second PPA for power generated from the 756MW Golden Plains Wind Farm – East with digital infrastructure company Equinix, who will take 20% of the energy and green certificates (LGCs) generated from the wind farm.

TagEnergy had already signed a first PPA with federal government-owned gentailer Snowy Hydro for 40% of the energy and LGCs in the middle of 2023.

The company expects to begin producing renewable energy from the first phase of the wind farm in the first quarter of 2025.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

State sets 75 pct renewable energy target as it transition away from coal by end of decade

State sets 75 per cent renewable energy target by 2030/31 to encourage private investment as…

27 October 2026

Snowy puts its hands out for government money, but hasn’t released business case to justify cost blowout

In previous resets, the government of the day and Snowy Hydro have touted the net…

27 October 2026

Australia’s top ranked home battery supplier unveils larger all-in-one BESS for commercial and industrial sites

Australia's leading home battery supplier offers bigger all-in-old battery solution for commercial and industrial sites…

27 October 2026

Letting data centres build first, catch up on renewables later could add $40 billion to power bills

Data centres should carry the cost of higher electricity rates if allowed to build now,…

26 October 2026

Well done, Angus: Taylor vows to slash Arena, home battery and EV funding to pay for promised tax cuts

Coalition leader Angus Taylor wants to scrap renewable energy agency, funding for home batteries and…

26 October 2026

Australia enjoys surge in wind, solar and battery projects, with $32.5 billion now financed or under construction

Across Australia, $32.5 billion of generation and storage is now under construction or at financial close,…

26 October 2026