Australia’s largest wind project seals energy offtake deal with Snowy Hydro

Published by

TagEnergy’s huge Golden Plains wind project has snared its first energy offtake deal, with the federal government-owned gentailer Snowy Hydro signing up to take 40 per cent of the electricity and large-scale generation certificates produced by the Victorian project.

The first 756MW stage of the up to 1.3GW wind farm is currently under construction near Rokewood in Victoria’s south west, with the first turbines going up from July. It will also include a big battery.

TagEnergy CEO Franck Woitiez says the deal with Snowy is the first PPA – but not the last – for the wind farm, which notably achieved financial close in November 2022 on a merchant basis.

“This landmark PPA with Snowy Hydro proves our strategy to progressively contract the energy production during construction and operation,” Woitiez said on Monday.

“It also reflects the confidence major industry players like Snowy Hydro have in our large-scale renewables project expertise,” he said.

Snowy Hydro chief commercial officer Gordon Wymer says the investment structure developed for Golden Plains has provided optimal outcomes for all stakeholders – including locking in a significant portion of Snowy’s energy and LGC needs.

“This has enabled Snowy to continue to expand its ability to provide clean, green, cost-effective renewable energy to our customers, and paves the way for further cooperation with TagEnergy on other developments,” Wymer said.

The $2bn, 122-turbine first stage of Golden Plains is expected to start producing renewable energy in the first quarter of 2025.

Woitiez says the huge project has generated significant interest from a range of potential offtake partners for its quality and location.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026

Australia’s first transmission loop between three states set to “fundamentally change” flow of electricity

Australia's first major transmission loop is now operating, and will be at full capacity by…

9 October 2026