Australia’s biggest battery – the 300MW/450MWh Victoria Big Battery near Geelong – has been registered and is about to begin production, but a supply shortfall is looming for future battery storage projects in Australia and around the world.

The Victoria big battery will be about double the size of its stablemate, the original Tesla big battery at Hornsdale, which was once the biggest in the world and was recently expanded to 150MW/194MWh.

Both batteries are owned by French-based renewable and battery storage developer Neoen and both are ground-breaking in their own way because they changed, and will change, the thinking about how the grid is managed thanks to their speed and flexibility.

Hornsdale broke open the gas cartel’s hold on the key network services market, and is now acting as a “virtual synchronous machine”, and the Victoria battery by delivering “virtual transmission” by allowing the amount of capacity on the main link between NSW and Victoria to be significantly increased.

The Victoria big battery on Tuesday was issued with two DUIDs (dispatchable unit identifiers) – VBBG1 and VBBL1 – by the Australian Energy Market Operator to reflect its dual roles of charging (load), and discharging (generation) in its activities.

It is understood that activities will commence as early as Wednesday, where it will be allowed to operate up to its first “hold point” of around 30MW.

Neoen only recently celebrated the “half way” mark of installations at the Geelong site, and much of the battery remains to the installed.

But the speed with which it has obtained registration contrasts sharply with the huge delays, sometimes more than a year, suffered by large scale wind and solar projects in Australia, including the country’s biggest wind project to date, the 530MW Stockyard Hill wind farm near Ballarat.

The Victoria big battery is using Tesla Megapack battery modules, sized at 3MWh each, as is the first big battery in NSW, the 50MW/75MWh Wallgrove big battery in western Sydney being built by Transgrid.

Together they form a major part of the record deliveries for Tesla in Q2, when it tripled its stationary battery storage deliveries to more than 1,240MWh, as the overall company delivered its first billion-dollar quarterly profit.

However, Tesla CEO Elon Musk warned that its flagship Megapack module has already been sold out to the end of 2022, and battery supplies were being hindered by the shortage of both battery cells and semi-conductor chips.

“We have a significant un-met demand in stationary storage,” Musk told the Tesla Q2 investor call on Tuesday morning (Australia time). “Megapack is basically sold out through the end of next year.”

Musk said there is also a massive backlog in the smaller Powerwall battery storage product used in homes and businesses, again caused by supply issues.

“Powerwall demand versus production is an insane mismatch,” Musk said. “Part of that is due to the semi-conductor issue. We use the same chips, so it is like ‘which one do you want to make – a car or a Powerwall’? We need to make cars, so Powerwall production has been reduced.”

Musk says if the supply blockages are eased, production of Powerwalls could reach one million a year, or 20,000 a week, but demand was even more than that.

And he said “vast amounts” of Megapacks will be needed by utilities as the world transitions to sustainable energy productions, and particularly wind and solar.

Tesla and other suppliers needed to produce around 1,000GWh of battery storage a year, maybe 2,000GWh a year. In the last 12 months, Tesla produced just 4GWh of stationary battery storage.

 

 

 

 

 

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

The deadly disease blinding the West to who is winning the energy transition

Western economists, journalists and analysts systematically underestimate China's technology leadership, especially on the decarbonisation of…

27 August 2026

Construction starts on network of community-scale batteries to help suburbs power through extreme heat

Work begins on $65 million network of eight community-scale batteries, which will support the grid…

27 August 2026

After Anthony Albanese’s fold on data centres, where might Chris Bowen be curtailed next?

Analysts and even state governments are trying to make sense of Albanese's backdown on data…

27 August 2026

Planning rules changed to stop long distance agitators hijacking wind, solar and battery approvals

Planning rules have been changed to stop long distance and often repeat agitators hijacking wind,…

27 August 2026

Offshore wind’s big boat and port problem – and the floating “feeder dock” that could help solve it

Australia faces a challenge in finding ships and ports capable of handling huge turbine parts…

27 August 2026

Gas network reforms panned for shifting cost of avoiding “death spiral” from investors to consumers

A package of reforms proposed to avoid a gas network death spiral has been described…

27 August 2026