AusNet pushes case for route through Victoria to unlock wind and solar

Published by

The final route of a massive electricity network upgrade that promises to unlock huge amounts of new large-scale wind and solar in western Victoria has been narrowed down to just a few alternative corridors, ahead of an updated proposal expected to be made mid-year.

ASX-listed AusNet Services this week unveiled the latest design for the Western Victoria Transmission Network Project, which proposes a new transmission line stretching nearly 200km from Bulgana, in Victoria’s west, to the north-western Melbourne suburb of Sydenham.

AusNet said the changes to the Western Victorian Transmission Network Project – pictured in the map below – brought it a step closer to being realised, as the first major grid upgrade for the state in 30 years and a “critical” piece of its renewable energy puzzle.

Image: AusNet Services
Image: AusNet Services

According to the Australian Energy Market Operator – which is responsible for the planning of the Victorian transmission network and which selected AusNet’s Mondo for the WVTNP job through a competitive tender – the state connected more new generators to its grid over the 2019-2020 period than in any other NEM state, or than in any previous reporting period.

This has been important progress for Victoria, which is working towards targets of 40% renewables by 2025 and 50% by 2030, but it has also laid bare the inadequacies of a grid that was built decades ago based on a centralised, coal-fired system.

In western Victoria, the problem has been particularly severe, leading to delays to the commissioning of completed wind and solar farms and constraints to the output of already operational projects – and giving the local network the unfortunate nickname, “Rhombus of Regret.”

As it stands, renewable energy in the region currently has a combined generation of approximately 4200MW connected, but according to AEMO’s estimations, with the right infrastructure it has the potential for a further 8600MW.

AusNet says that unlocking these vast reserves and making them available to the national electricity market will also play a key role in network reliability and the further reduction of the state’s electricity prices.

“Transmission upgrades are a major step toward enabling the potential of Australia’s green energy boom, this project is a major piece of the puzzle to facilitate that in Victoria,” said AusNet’s executive project director, Stephanie McGregor.

“Once built the Western Victoria Transmission Network Project is expected to deliver substantial benefits to electricity consumers and the region over the life of the project.”

But just as transmission upgrades like this one promise to open the floodgates to renewables, they are also shaping up as the new battlefront for the industry, as regional communities push back against the arrival of massive transmission towers and overhead lines – and in this case a new terminal station – in their back yards.

At least one community group has come out firing already, claiming that the WVTNP will “cause immeasurable economic damage to local farmers and irreparable harm to the environment and landscape – to say nothing of the amenity and liveability of our region and the wellbeing of residents.”

The group, a coalition of local landowners, residents and businesses that calls itself Stop AusNet’s Towers, is calling on governments to guarantee “full, genuine consultation, conduct and independent analysis” of alternatives to overhead lines, including underground options.

“We support renewable energy and want green energy generated in Western Victoria connected to the rest of the state. But overhead powerlines are unsafe, inefficient and will destroy our precious landscape,” said the group’s spokeswoman Emma Muir. “Underground transmission might be more expensive to install, but it’s safer and more efficient.”

The Victorian government, to this end, just last week announced the establishment of a separate entity, called VicGrid, to oversee all of the state’s transmission upgrade projects and – crucially – work with local communities and Traditional Owners to ensure their concerns are being heard.

“Our plan will deliver investment for regional Victoria, and we aim to build the social licence before proceeding,” Victorian’s energy minister Lily D’Ambrosio said on announcing the new body.

AusNet, meanwhile, has this week invited affected communities to nominate consultation groups, to enhance communication both within the community and between the community and the project. A series of community information sessions will also be held in the various communities starting in March.

The latest design for the WVTNP proposes no changes to the new high-voltage electricity line starting at the Bulgana Terminal Station near Stawell alongside the existing line to the Waubra Terminal Station (section one), nor to section three, from Creswick North, east to Railway Weir, north of Gordon. But it does offer three options for the corridior that will run south Waubra to Creswick North; and two options for section four, which runs from Railway Weir north of Gordon, to Coimadai.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024