Storage

Auditor-general slams management of Snowy 2.0 as more delays loom and project costs blow out

Published by

The federal auditor-general has slammed the management of Australia’s biggest renewable energy project, Snowy 2.0, citing multiple failures and pointing to yet more delays for the project that is already vastly over budget.

The report by the A-G, released on Thursday, is the first to be completed since Snowy Hydro announced a project “re-set” in 2023 that conceded the costs of the huge pumped hydro facility had blown out to $12 billion, and faced yet more delays, pushing the expected completion date out from May, 2026, to the end of 2028.

The project costs appear set to blow out once again to around $20 billion, and some argue that the total costs including interest and transmission is closer to $40 billion. The full extent will be revealed soon after an intensive none-month, line by line analysis of project costs.

The A-G report is critical of the actions of both the board and the management since the re-set.

“Since then, (management) has not effectively held the contractors to account for delivery, has not effectively implemented measures that were intended to manage project risks, and does not have access to quality data that would allow it to appropriately monitor the project,” the report says.

On the board oversight, it writes: “While the board challenged information provided to it by management, sufficient board consideration of the project reset risks was not demonstrated.”

Snowy Hydro has been prepping the public for the latest blowout in costs, producing reports that justify the project’s importance to the green energy transition, and inviting media and influencers to publish favourable reports about its importance to grid security and reliability.

But it has also hinted at yet more delays beyond the current deadline of late 2028. CEO Dennis Barnes told the AFR last month that the company was “not feeling that comfortable” about meeting the deadline.

The A-G report highlights why, noting that “line of sight” calculations suggest commercial operations will not be achieved until September, 2029, and as at July last year was 262 days behind the December, 2028 schedule.

In fact, the project had not been on that schedule since late 2023, although the number of days behind schedule had reduced from 453 in December, 2023, but increased considerably from 114 in December, 2024.

Screenshot

The costs of Snowy 2.0 have blown out ten-fold since the original $2 billion claim made when the project was first announced in early 2017.

Later that year, a feasibility report suggested a cost of between $3.8 billion and $4.5 billion, before this was lifted to $6.1 billion in 2018 when the first major contracts were signed and the final investment decision was reached.

That cost then doubled again to $12 billion after the 2023 reset, and the A-G report says most of this had already been spent by May this year. It now seems destined to leap to around $20 billion – on project costs alone – in the latest review.

Previous A-G reports have highlighted multiple failings by Snowy Hydro, including its failure to properly assess the geological conditions that have proved problematic and been a major cause of delays and cost blowouts.

The latest A-G report said significant deficiencies in Snowy Hydro’s project management include the following.

  • – Key quality controls have not been effectively implemented.
  • – There is no agreed baseline schedule for the project.
  • – Snowy Hydro has reported that productivity gains assumed at reset are proving difficult to realise.
  • – Snowy Hydro does not have a robust understanding of the forecast cost to complete of the project.
  • – The incentive framework is not working as intended.
  • – Snowy Hydro does not have adequate arrangements to monitor the impact of adjustments on value for money.

The A-G report made five recommendations, mostly around improving its project management skills. Snowy Hydro agree to four of these recommendations, but only partially agreed to a fifth that related to the need to develop regular public reports on project schedule that includes information on project progress against published targets.

“Public reporting and internal management forecasting serve different purposes and utilise different methodologies appropriate to those functions,” the company said in its response.

“Internal risk-adjusted and critical path forecasting tools are used to support project management and assurance activities but are not typically adopted for external reporting due to commercial sensitivities.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Featured

Recent Posts

Developer pitches huge 1 gigawatt new wind project for Queensland’s north

Developer unveils its second giga-scale renewable energy project proposal this week, with the website launch…

19 June 2026

Macquarie storage offshoot presents two four-hour battery projects for federal green tick

Storage specialist has nine projects in its portfolio in Australia, with two going public on…

18 June 2026

Frequency penalties are costing some solar farms millions, but this is the market working

Data shows solar farms and big batteries are the biggest loser and winner following changes…

18 June 2026

PV research powerhouse wins fresh Arena funding to pursue ultra-low cost solar

Australia's flagship solar research program has secured another six years of federal funding to continue…

18 June 2026

LGC prices have more than doubled in a few weeks, but who are the buyers – data centres or speculators?

The LGC market is having a moment, doubling in price in a matter of weeks,…

18 June 2026

Demand response trials could open up more than 1 gigawatt of extra grid capacity

This may be one of the most important trials underway today, at least if data…

18 June 2026