Snowy 2.0 budget to be exhausted in coming months, ratings agency says, as gas plant hit by new delays

Published by

The federal government owned Snowy Hydro is expected to exhaust its existing $12 billion budget for the controversial Snowy 2.0 pumped hydro scheme in coming months, as news of yet more delays at its equally controversial Hunter gas project come to light.

Global ratings agency S&P issued a note yesterday warning of a potential downgrade to the rating of some of its debt – which will increase costs – citing the ongoing cost blowouts and delays at both projects.

Snowy Hydro has already admitted its latest official estimate of $12 billion capex for the 2,200 MW Snowy 2.0 will be breached, but has said it will take it up to nine months to discover exactly by how much, such are the deep complexities of Australia’s biggest ever storage project.

“We assume capex for Snowy 2.0 will reach $12 billion in fiscal 2026 (ending June 30),” S&P writes in the report, noting that the project is only 70 per cent complete as at the start of this year. “The project is facing persistent and material cost pressures, prompting a reassessment of the project costs.”

S&P also raised flags over the 660 MW Hunter gas project, another Coalition-led initiative, which is also facing significant cost over-runs and yet more delays in its commissioning process.

“The HPP project has experienced extended periods of extreme weather and other factors, including commissioning complexities, that have impacted its cost and timeline,” S&P notes.

That plant has now completed its commissioning process using gas as a fuel, but is now considering delaying testing for the use of diesel, given the current fuel demand issues, a company spokesman was quoted as saying by the AFR on Thursday..

Hunter gas, which was supposed to be online in 2023, is now expected to come online in May – likely without the diesel component in the short term – and at least double the original cost of $610 million.

The budget blew out to $950 million in 2023, then to $1.3 billion by late 2024, and the company is not sure what the final cost will be. “The final cost will be known when commissioning is complete,” a company spokesman was quoted as saying by the AFR.

S&P notes that the federal government has provided $5.98 billion of equity support since 2021, including $1.4 billion of preference shares and is now also providing a $4.5 billion shareholder loan for construction of Snowy 2.0, of which A$3.3 billion remains undrawn – which means despite the budget overruns it will not run out of money.

“While the extent of the cost overrun at Snowy 2.0 remains uncertain, we expect additional shareholder support will be provided after the project costs have been reassessed,” S&P writes.

“We could lower our rating on Snowy Hydro if timely and adequate support from the government is not forthcoming to support the balance sheet.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.



Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Massive 1.1 GW Queensland wind project that overcame state pause secures federal approval

A mammoth 1.1 GW wind project that was paused in 2025 by the Queensland LNP…

15 July 2026

Coal giant gets nod to convert retired mine into solar and pumped hydro powerhouse with 12 hours storage

State approves plans of Australia's largest listed coal miner to transform a retired mine site…

15 July 2026

Renewables sector learning from messy failures after oil company collapses with $200m clean up bill

Another oil and gas company collapse raises new concerns about who picks up massive clean…

15 July 2026

Data centres will have “legal obligation” to BYO renewables, says PM, but LNP looms as spoiler

PM says data centres will have a "legal obligation" to meet their own energy needs…

15 July 2026

SwitchedOn podcast: Why the booming home battery market is staying clear of virtual power plants

Despite the potential for lower bills, and a stronger grid, most battery owners still aren't…

15 July 2026

Flood-prone rugby fields, gaps in regional health: First round of REZ grants back 46 community projects

New drainage systems for flood-prone sports ground and a new community health hub are among…

15 July 2026