ARENA backs Qld solar farm that will supply 10% of Australia’s large-scale solar

Published by

A 25MW solar farm being built in the central-western Queensland town of Barcaldine will provide about 10 per cent of Australia’s large-scale solar electricity, according to ARENA, which announced this week it would provide $22.8 million to support the massive project’s construction.

The Barcaldine Regional Community Solar Farm, which once completed will be the state’s largest solar array, was first proposed to the local community in March, by its developers Kingsway Europe and the Australian arm of Elecnor.

The duo formed a company called Barcaldine Remote Community Solar Farm to plan and develop the project, which is expected to generate 53,000 megawatt hours of renewable energy each year, and may incorporate battery storage once completed in April 2017.

The single-axis tracking solar PV plant will also reduce peak demand pressures and provide voltage control for the local network, resulting in a more robust electricity supply to the sparsely populated and remote Barcaldine region.

ARENA CEO Ivor Frischknecht says the project will demonstrate the benefits renewable generation can deliver when located at the edges of Australia’s sprawling national electricity network.

“Fringe-of-grid locations in regional Australia face a number of challenges with reliability and outages caused by network constraints and a lack of infrastructure,” Frischknecht said.

“This project will serve as a test case showing how the network benefits from distributed renewable energy can improve network efficiency, and potentially enable solar plants to access an extra revenue stream through network support payments.”

Frischknecht said the potential for adding battery storage would also be examined.

“This could allow the solar plant to work in tandem with the existing gas plant during a line outage, operating as an ‘island’ network independent to the main grid,” he said.

“There is a clear value proposition for large-scale solar in the Barcaldine area, which has an excellent solar resource and experiences voltage and frequency control issues as well as load management challenges.”

As well as ARENA’s contribution, the Clean Energy Finance Corporation has provided $20 million in debt finance to the $69 million project.

CEFC CEO Oliver Yates said it was projects like this that showcased solar power as a competitive source of energy.


Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Renew Economy is hiring to expand its team and deepen its coverage of the energy and EV transition

Renew Economy is looking to expand its team. If you are interested in the transition…

17 December 2024

Mingyang’s two-headed floating wind turbine begins operations, despite fractures in giant blades

Mingyang says its two-headed floating offshore wind platform has begun operations despite reports of blade…

17 December 2024

Regulator rejects Basslink bid in draft decision on troubled undersea cable

A bid to convert the Basslink undersea cable into a regulated transmission asset knocked back…

17 December 2024

“Tidal wave” of big batteries and record solar and wind put 2030 renewables target within reach

A "tidal wave" of big batteries and record amounts of new solar and wind are…

17 December 2024

Tasmania port tapped as key offshore wind hub, days after declaration of Bass Strait zone

Tasmanian port plans to play host to renewable energy terminal and serve as a key…

17 December 2024

“Mind blowing:” Battery cell prices plunge in China’s biggest energy storage auction

Latest battery storage auction prices in China stun analysts with another big price fall that…

17 December 2024