ARENA-backed Manildra Solar Farm reaches financial close

Published by

A 48.5MW solar farm being built by US solar developer and module manufacturer First Solar in central western New South Wales has reached financial close, becoming the latest project selected from ARENA’s groundbreaking large-scale solar competitive round to do so.

First Solar said on Monday that the project had reached financial close, an achievement that comes less than four months after the company signed with EnergyAustralia to buy the output from the solar farm, as part of a 13-year Power Purchase Agreement.

At the time, First Solar’s head of Australian development Jack Curtis said he could not reveal the pricing details of the Manildra PPA, but said unsubsidised solar projects were currently priced at around $80-$90/MWh.

Curtis said the ARENA funding round – Manildra was supported by $9.8 million of grant funding from the Australian Renewable Energy Agency – had helped a recent crop of solar projects meet that target band, but also noted that costs in Australia were falling quickly with the establishment of new solar supply chains and manufacturing and installation efficiency.

“Today’s milestone is a testament to the ability and experience of First Solar’s development and delivery team, and we congratulate ARENA and EnergyAustralia on their commitment to commercially viable projects,” saidCurtis.

“We have witnessed unprecedented cost reductions in large-scale solar in recent years. As the appetite for this asset class continues to grow, timely and reliable project delivery will be the strongest driver of future cost reductions, cementing solar as a competitive energy source in Australia,” he said.

EnergyAustralia managing director Catherine Tanna described the Manildra Solar Farm as a great example of the projects that would underpin the future of energy in Australia – the company has also recently signed PPAs for a 113MW wind farm in NSW, a 60MW solar project in Victoria and a 142MW solar farm in Queensland.

“Customers rightly expect access to reliable, affordable and cleaner supplies of energy which means the industry needs to evolve,” Tanna said in a statement on Monday.

First Solar said RCR O’Donnell Griffin had been appointed for the engineering, procurement and construction of the project, the latter of which is set to begin within months.

“Construction will soon begin at the site, creating new economic opportunities for Australian businesses and families in the local region,” ARENA CEO Ivor Frischknecht said of the Manildra project.

“By supporting innovators like First Solar, ARENA has fast-tracked the development of substantial new Australian industries like the large-scale solar sector, which is now on the cusp of being commercial.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026

Australia’s first transmission loop between three states set to “fundamentally change” flow of electricity

Australia's first major transmission loop is now operating, and will be at full capacity by…

9 October 2026