Another major industrial user has agreed to “voluntarily” reduce their electricity demand as Tasmania continues to grapple with its biggest ever energy crisis.
Hydro Tasmania on Tuesday announced that paper milling giant Norske Skog has agreed to close one mill and reduce demand by 43MW as the energy authorities work out how to deal with the loss of the Basslink connection to the mainland and the fall in dam levels to their lowest levels ever.
Hydro Tasmania is currently rushing in 200MW of diesel generation as a stop gap measure to ensure there is enough supply. It has already switched back on the Tamar Valley gas plant, sending average prices more than four-fold higher to around $180/MWh.
The situation has led many to wonder why the government did not invest more in locally sourced wind energy, or encourage more rooftop solar – both options that would have been substantially cheaper than gas. The diesel generation will cause wholesale electricity prices to double again.
Hydro Tasmania says it is facing operating losses this year as it brings in more expensive generation to allow it to conserve its depleting hydro resources as long as possible. Dam levels are now down to just 16.1 per cent.
It said Norske Skog will voluntarily reduce load at its Boyer Mill for one week, starting from the middle of next week. The reduction will involve the closure of one of the mill’s two paper machines and associated pulp mill. These actions will have no effect on the Boyer workforce.
Andrew Catchpole, the acting CEO of Hydro Tasmania, said in a statement that the generation from gas and “temporary” diesel, along with voluntary load reductions by large consumers, will be “well in excess of the import capacity” of Basslink.
“This will ensure Tasmanian demand can be met, even with a prolonged Basslink outage.”
Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…
In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…
In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…
CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…
Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…
The builder of Australia's biggest battery project describes the country's long stringy grid as like…