Another big industrial trims demand as Tasmania energy crisis deepens

Published by

Another major industrial user has agreed to “voluntarily” reduce their electricity demand as Tasmania continues to grapple with its biggest ever energy crisis.

Hydro Tasmania on Tuesday announced that paper milling giant Norske Skog has agreed to close one mill and reduce demand by 43MW as the energy authorities work out how to deal with the loss of the Basslink connection to the mainland and the fall in dam levels to their lowest levels ever.

The decision by Norske Skog takes total demand cuts from big industrial users to more than 110MW, following similar offers of 32-40MW by the Bell Bay aluminium smelter and 30MW from TEMPCO, the local manganese alloy factory.

Hydro Tasmania is currently rushing in 200MW of diesel generation as a stop gap measure to ensure there is enough supply. It has already switched back on the Tamar Valley gas plant, sending average prices more than four-fold higher to around $180/MWh.

The situation has led many to wonder why the government did not invest more in locally sourced wind energy, or encourage more rooftop solar – both options that would have been substantially cheaper than gas. The diesel generation will cause wholesale electricity prices to double again.

Hydro Tasmania says it is facing operating losses this year as it brings in more expensive generation to allow it to conserve its depleting hydro resources as long as possible. Dam levels are now down to just 16.1 per cent.

It said Norske Skog will voluntarily reduce load at its Boyer Mill for one week, starting from the middle of next week. The reduction will involve the closure of one of the mill’s two paper machines and associated pulp mill. These actions will have no effect on the Boyer workforce.

Andrew Catchpole, the acting CEO of Hydro Tasmania, said in a statement that the generation from gas and “temporary” diesel, along with voluntary load reductions by large consumers, will be “well in excess of the import capacity” of Basslink.

“This will ensure Tasmanian demand can be met, even with a prolonged Basslink outage.”

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Woodside quits US concentrated solar project, puts green hydrogen plans on hold

In a decision Woodside says is "not particularly" related to America's new fossil fuel focus,…

22 January 2025

Fact check: No, a Queensland solar farm was not “smashed” by wild weather

A social media post featuring a fake news report is spreading a false claim about…

22 January 2025

Santos hits pause on massive Australian oil and gas project, shifts attention to US

As Trump confirms plans to "drill baby, drill" Santos hits pause on a $3bn-plus oil…

22 January 2025

Marinus Link moves closer to construction as short-list narrows down to two contenders

Marinus Link has narrowed the field for who will build the onshore infrastructure to two…

22 January 2025

Big battery joins solar farm to complete “cutting edge” hybrid renewables system

Vena Energy says it has completed Australia's largest utility-scale hybrid renewable facility with a single…

22 January 2025

Quinbrook seals record finance deal to build huge “Supernode” data centre battery

Developer Quinbrook Infrastructure starts the year with the biggest ever funding deal for a battery…

22 January 2025