Solar

Another 115MW solar farm starts sending power to the grid in NSW

Published by

Another new solar farm has begun sending power to the grid in New South Wales, with the 115MW (ac) Metz facility recording its first output this week.

Metz, owned by FRV and Omers Infrastructure, is the biggest solar farm in northern NSW and is located in the heart of the New England electorate of Nationals leader and deputy prime minister and renewable energy enthusiast Barnaby Joyce.

The solar farm is at the start of the commissioning process, and will gradually test all its inverters before ramping up through the various hold point tests defined by the Australian Energy Mark Operator. It is expected to reach full production in a few months.

Source: NEMLog

Metz is one of nine big solar farm projects being built by FRV in Australia, with the latest development being the Sebastapol solar farm, also in NSW, reaching full production (pictured above). Both projects have been built by Beon Energy Solutions.

Metz is contracted to supply green power to Snowy Hydro.

“We are excited to see another FRV’s project start injecting clean electricity into the grid and we look forward to see the plant at its full capacity soon”. FRV’s managing director in Australia, Carlo Frigerio, said in an emailed statement.

See RenewEconomy’s Large Scale Solar Farm Map of Australia

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024