Zinfra has been awarded the construction contract to build the connection assets on behalf of AusNet Services as part of the construction of the Stockyard Hill Wind Farm.

Located on farmland approximately 45km south of Ballarat, Victoria, the Stockyard Hill Wind Farm (SHWF) will have a total expected capacity of around 530MW from 149 turbines. Once completed, SHWF will be the largest wind farm in the country and is expected to provide electricity for 391,000 Victorian homes.

Zinfra’s scope of works for this contract includes the complete construction of 70km of 132kV transmission line connecting the 3 Wind Farm Collector Substations to the greenfield Terminal Station at Haunted Gully; procurement for all the materials associated with the 132kV transmission line; complete construction of the 500kV/132kV Haunted Gully Terminal Station including all civil, structural and electrical works; and construction of the interface works and cut-over to re-align the existing 500kV transmission line (the main connection between VIC and SA) and connect the Haunted Gully Terminal Station.

Preliminary works have already commenced on this project and Zinfra is expected to mobilise on site by July.

Zinfra’s highly regarded transmission lines crews, electricians and project management teams will deliver the majority of the construction works, with Zinfra employing up to 100 people at peak times during the construction of the transmission line and terminal station.

Zinfra has been working closely and collaboratively with AusNet Services to secure this project since 2013.

Zinfra General Manager Projects, Paul Birighitti commented, “We are thrilled to be working on this significant project for AusNet Services, leveraging our core capability in the power sector, into the renewables sector.”

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024