Yarranlea solar farm joins the grid in Queensland

Published by

The 100MW Yarranlea solar farm has become the latest – and the 23rd – large scale solar farm to join the grid in Queensland, after injecting its first power output last week.

The Yarranlea installation – owned by Risen Energy and located 50kms south west of Toowoomba, in the state’s Darling Downs region – completed its mechanical installation late last year and expected to complete the commissioning process in the current quarter.

The project has not been picked up by the majority of market data-minders, but was by Paul McArdle at Global-Roam, the providers of RenewEconomy’s popular NEM-Watch widget, and he sent us this graph below.

All new wind and solar farms need to go through rigorous testing processes and protocols, and usually go through a series of “holding points” that limits their output at various levels until the network owner and the grid operator is satisfied it can move forward.

Risen Energy has said it intends to add battery storage to the facility some time in the future, and intends to operate the project on a “merchant” basis, meaning it will take the spot price for sales into the wholesale market. The facility has a projected 30-year life. Risen Energy was not available for comment on Monday.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024