Construction has started on the 250MW/500MWh Swanbank Battery south of Brisbane, setting in progress one of Queensland’s biggest battery energy storage systems, and the first to be built by the state’s publicly owned utility CleanCo.

The $330 million big battery is being developed by CleanCo in partnership with Tesla and Yurika at the site of the former Swanbank B coal-fired power plant outside Ipswich, as part of the Swanbank Clean Energy Hub.

The state Labor government says the big battery will have the capacity to store enough energy – largely from solar generated across local rooftops – to power more than two-thirds of Ipswich for two hours each night when demand rises as the sun sets.

The goal is to have the site energised by mid-2025, as part of the Queensland Labor government’s plan to shift the state to 70 per cent renewables by 2032, and to the newly legislated target of 75 per cent renewables by 2035.

“It’s because of new technologies like this that we will reach the ambitious energy targets put before parliament,” said Queensland premier Steven Miles on Monday.

“Renewables are driving down the spot wholesale price of power below zero, which is why we will continue to invest in them.”

CleanCo CEO Tom Metcalfe says the BESS marks the beginning of the Swanbank Power Station’s “transformative journey” away from fossil fuels and towards renewables.

Once part of a precinct of coal-fired power stations – Swanbank A, B, C and D – the gas-fired Swanbank E remains the only operating power station on the site.

“This is the beginning of a new era for Swanbank and CleanCo is proud to be the custodian of a site which has evolved and adapted with Queensland’s energy landscape from coal to gas and now new battery technologies,” Metcalfe said on Monday.

“The Swanbank Battery will add significant capacity for CleanCo to supply our customers with competitively priced, reliable clean energy around the clock,” he said.

State energy minister Mick de Brenni says the conversion of the Swanbank site to a Clean Energy Hub will also help to provide job security for the local workforce.

The battery project, alone, backed by $330 million in funding from the Queensland Renewable Energy and Hydrogen Jobs Fund, is expected to create around 60 jobs during construction and up to 10 full-time jobs in operation.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024