Work stops on Forrest’s Clarke Creek wind farm as project managers changed

Published by

Work on one of the biggest wind projects in Australia has come to an abrupt halt after the owners, Andrew Forrest’s Squadron Energy, decided to change project managers and take over the running of the Clarke Creek wind project.

The 450MW project in central Queensland is the first stage of an ambitious multi-gigawatt renewable precinct to be built by Squadron Energy, which recently paid around $4 billion for the renewable developer CWP, which has expertise in building large scale wind and solar projects.

The irony is that the project manager being replaced, Windlab, is another company in Forrest’s portfolio. His private interests own 75 per cent of that company, and it is thought that Squadron wanted the contract brought in under a wholly owned company.

The change of project manager meant a change of construction equipment, and all work abruptly ceased on the project on Wednesday afternoon as equipment was removed.

It is understood the timing of the changeover also comes before the deliver of the project’s major components, which will include some logistically challenging deliveries of huge turbines and blades along a 300km route.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024