Windlab’s solar-wind-battery project finally connected to Queensland grid

Published by

Windlab’s world-leading solar, wind and battery project at the Kennedy Energy Park in north Queensland has finally been connected to the grid and energised after an eight month delay.

The construction of the Kennedy hub – combining 43MW of wind, 15MW of solar and a 2MW/4MWh Tesla battery – was completed in December but has been held up by the complexity of generation performance standards, one of a number of projects that have had to wait on the sidelines as they sought to negotiate strict new standards.

The combination of wind, solar and a battery makes it the first of its type on a major grid in the world, but Windlab says its issue were complicated by the requirement to add both a statcom (for voltage) and a synchronous condenser (for system strength), the first project to do so in the Ergon network.

Many new wind and solar farms in Australia are now required to install a synchronous condenser to ensure system strength is retained. These have cost an average $25 million (although it is understood that Windlab’s is smaller than most), and has added significantly to project costs.

Windlab also had problems with its EPC contractor, declaring force majeure earlier this year because of the delays in production caused by the connection issues and flooding at the site.

“Nearly all renewable generators in Australia have found grid connection challenging in the past 18 months,” Windlab executive chairman and CEO Roger Price said in a statement.

“Being the first project to implement both a statcom and synchronous condenser in Ergon’s network has meant Kennedy is no exception.

“However, the persistence and technical capability of the (Windlab) team has paid off. We look forward to completing the registration and commissioning work over coming months as the project is placed into full service.”

The Kennedy facility is connected but will not be able to export electricity into the grid until the middle of the month because of a compulsory “hold point zero” period that will allow the network operator to conduct background power quality testing.

The project will then commence commissioning and testing, and progressively exporting electricity to the network through a series of further “hold points”, initially under a 5MW export limit until AEMO registers the project as a generator in September.

Formal commercial operation is expected later in the year.

Kennedy Energy Park is jointly developed and owned by Windlab and Eurus Energy Holdings. It is located near Hughenden in North Queensland. Windlab has previously suggested that project could be transformed into a major 1200MW plant combining the three technologies, but this would require a major grid upgrade for the area.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026