Windlab disputes AEMO 2-year delay for Kennedy wind-solar-storage hub

Published by

There is growing confusion over the status of Windlab’s world-leading wind-solar-battery energy hub at Kennedy in north Queensland.

On Thursday, in a note to its Electricity Statement of Opportunities, the Australian Energy Market Operator said the anticipated commissioning of the Kennedy energy hub had been delayed by nearly two years from August, 2019, to July, 2021.

This was news to Windlab, which still expects the already delayed project to be in full commercial operation by the end of this year.

“Windlab was not consulted by AEMO about this assumption and is not aware of the basis on which AEMO arrived at this assumption,” it said in a statement to the ASX.

“Windlab will advise AEMO that it considers their assumptions to be too conservative.”

It added that it had been generating electricity  since mid August, and was operating under a 5MW export limit. All wind and solar farms have to go through various limited “hold points” to prove their equipment is working properly.

The Kennedy energy hub – combining 43MW of wind, 15MW of solar and a 4MW/4MWh Tesla battery – is a first of its kind project for a main grid, although similar projects have been announced since.

Windlab completed the building of the project late last year, but had to wait eight months before it was connected to the grid.

The reasons for the delay are not clear. It is one of a number of projects suffering such delays, often caused by strict new connection standards, lack of grid capacity, the need for new equipment and/or the shortage of resources from networks and the market operator. Kennedy had already been required to add a synchronous condenser and a statcom to the project.

Earlier, an AEMO spokesman said in an emailed statement after RenewEconomy asked about the delay:

“In line with our published methodology for producing Reliability Forecasts under the RRO (retailer reliability obligation), we have excluded the possible contribution from Kennedy Energy Park for the first summer due to uncertainty on whether they will be able to generate consistently in the short-term.

“As system security is our highest priority, we need to ensure that any outstanding stability, compliance and model issues are resolved before registration and commissioning.”

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024