Windlab dispute with contractors deepens over delays to Kennedy energy hub

Published by

Listed renewable energy developer Windlab says it faces another four or five months of delays before its world-leading wind-solar-battery hub at the Kennedy Energy Park in north Queensland is on line, and says it is in dispute with its EPC contractors.

Windlab says the 62MW Kennedy facility – which combines 42MW of wind, 15MW of solar, and 4MWh of battery storage – is already 13 months late and is not forecast by the EPC contractors – Vestas and Qanta Services) to reach full commercial operations for a further four to five months.

Windlab has sought liquidate damages over the delays and its financial impacts in the last financial year, and says the EPC contractors have failed to deliver a “fully-functioning, compliant generator performance standard (GPS), which is essential to gain registration by the Australian Energy Market Operator.

In a statement to the ASX on Tuesday, Windlab says while it is seeking damages from the EPC contractors, they in turn are seeking “milestone” payments and has now taken the dispute for arbitration under the Queensland Building Industry Fairness Act.

“The EPC contractor also made numerous claims for extensions of time and variations against the EPC contract which are not accepted by KEP (Kennedy Energy Park), the statement says.

“Windlab believes that Kennedy Energy Park has recourse under the terms of the EPC contract for these ongoing delays and costs if substantive legal proceedings become necessary.”

The project is the world’s first to combine wind, solar and batteries at such scale in a single facility on a main grid, and was largely complete late last year.

Nearly all new wind and solar projects in Australia are experiencing delays, for a number of reasons but mostly to do with connections and commissioning. Seeking liquidated damages from EPC contractors has become a common sight in the industry, and led to a review of how those contracts are structured.

Neither Windlab nor the contractors have been prepared to discuss the nature of the issues at Kennedy Energy Hub, where a small synchronous condenser has also been installed.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

No concrete, no B-doubles: Major solar and battery project promises ultra-light touch

A large-scale solar and battery project seeking federal environmental approval proposes to use an innovative…

15 February 2026

If we’re going to hold an inquiry into the life cycle of solar, why not coal and gas?

Australia's solar waste investigation raises an interesting question of consistency. Where is the inquiry into…

15 February 2026

“Well done, Angus:” Liberals elect “failed” former energy minister to lead party

Angus Taylor has been elected leader of the federal Liberal Party, deposing Sussan Ley just…

13 February 2026

New five-hour battery reaches financial close, next to existing gas generator in renewable hotspot

Another five-hour battery reaches financial close, this one to piggy back over an existing gas…

13 February 2026

Energy Insiders Podcast: Why batteries are getting bigger and marrying solar

Sam Reynolds, the head of Octopus Australia, on why he hopes to build the country's…

13 February 2026

The little battery that could pave the way for ageing coal generators to be shut down on schedule

Concern about system security has already delayed the closure of Australia's biggest coal generator. But…

13 February 2026