Wind farms face new constraints in Victoria’s troubled “rhombus of regret”

Published by

New constraints have been imposed on large scale wind farms in the north-west Victoria as a result of efforts by the Australian Energy Market Operator to limit the size of potential “contingencies” on the grid.

AEMO currently seeks to limit a single contingency size to 600 MW, so it can make sure it has the resource at its disposal should a large coal unit or a transmission line trip.

A new assessment has discovered that the total output of renewable projects that form part of a 220 kV Generator Fast Trip Scheme amounts to up to 1,000 MW – more than it is comfortable dealing with in the event of a trip.

As a result, AEMO has imposed a new constraint – imposed from Tuesday this week – that limits the combined output of these generators – located on a troubled part of the grid known as the “rhombus of regret” to 750 MW.

Those affected are further along the 220 kV transmission line from the Waubra wind farm. The identities have not been publicly revealed but are believed to include the Crowlands, Ararat, Bulgana and Murra Warra wind farms.

AEMO says the potential constraints were agreed as part of the connection agreements for the affected projects, but says it will be temporary and will be relaxed once the new Western Renewables Link transmission line is completed.

The new constraint equation will limit the total generation output for generators associated with the GFT1 scheme (and inherent tripping of Waubra WF) to a limit of 750MW.

AEMO says the restrictions on output are likely to be limited as these wind are generally more impacted by other constraints (presumably mostly economic ones caused by negative wholesale prices), meaning that total output of the affected generators is normally below the limit, even under high wind conditions.

Want the latest clean energy news delivered straight to your inbox? Join more than 26,000 others and subscribe to our free daily newsletter.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Fortescue accelerates away from oil: doing what Australia should be doing on the fuel crisis

Fortescue is showing the future to the rest of Australia: Batteries and electrification replacing barrels…

10 April 2026

For First Nations communities, energy insecurity is not new. But the shift to renewables is more urgent than ever

In remote First Nations communities primarily reliant on diesel power stations, the steep price hikes…

10 April 2026

“An own goal that we don’t need:” Investor group sounds alarm over new tax on renewables

Investor group "dismayed" at draft reforms to the Capital Gains Tax it says will deter…

10 April 2026

“2 systems every 5 minutes:” Home battery records tumble as regulator issues fresh warning to installers

Newly minted leader of Australia's home battery market claims stunning new installation record, as regulator…

10 April 2026

Independent panel approves another big battery sent for review by long-distance haters

Independent regulator approves big battery proposed for next to a waste-water treatment plant, after it…

10 April 2026

Energy Insiders Podcast: Why wind projects are stalled at the gate

Large scale wind projects are not getting finance and are not getting built. CEIG's Richie…

10 April 2026