Renewables

Wind farms face new constraints in Victoria’s troubled “rhombus of regret”

Published by

New constraints have been imposed on large scale wind farms in the north-west Victoria as a result of efforts by the Australian Energy Market Operator to limit the size of potential “contingencies” on the grid.

AEMO currently seeks to limit a single contingency size to 600 MW, so it can make sure it has the resource at its disposal should a large coal unit or a transmission line trip.

A new assessment has discovered that the total output of renewable projects that form part of a 220 kV Generator Fast Trip Scheme amounts to up to 1,000 MW – more than it is comfortable dealing with in the event of a trip.

As a result, AEMO has imposed a new constraint – imposed from Tuesday this week – that limits the combined output of these generators – located on a troubled part of the grid known as the “rhombus of regret” to 750 MW.

Those affected are further along the 220 kV transmission line from the Waubra wind farm. The identities have not been publicly revealed but are believed to include the Crowlands, Ararat, Bulgana and Murra Warra wind farms.

AEMO says the potential constraints were agreed as part of the connection agreements for the affected projects, but says it will be temporary and will be relaxed once the new Western Renewables Link transmission line is completed.

The new constraint equation will limit the total generation output for generators associated with the GFT1 scheme (and inherent tripping of Waubra WF) to a limit of 750MW.

AEMO says the restrictions on output are likely to be limited as these wind are generally more impacted by other constraints (presumably mostly economic ones caused by negative wholesale prices), meaning that total output of the affected generators is normally below the limit, even under high wind conditions.

Want the latest clean energy news delivered straight to your inbox? Join more than 26,000 others and subscribe to our free daily newsletter.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Golden moment: Australia’s biggest wind farm becomes first to reach 1 GW of output

Australia's biggest operating wind farm has set a stunning new record, becoming the first in…

12 June 2026

The quiet battery: What household batteries reveal about flexibility before full orchestration

The passive battery is not a new phenomenon. What is new is that its value…

12 June 2026

State utility eyes 8-12 hour energy storage investment after “standout” success of four-hour big battery

State-owned utility says it is in discussions to invest in non-lithium technologies with up to…

12 June 2026

Depleted batteries and very expensive gas: How a two-day heatwave led to a near doubling of quarterly prices

Batteries have been protecting consumers from price spikes in most states over summer. But they…

12 June 2026

Solar Insiders Podcast: The public power company plugging the gaps

State Electricity Commission CEO Chris Miller on how the government-owned energy company is filling gaps…

12 June 2026

Australia’s electricity market needs better price signals that reflect local conditions

Australia’s electricity prices ignore location, even though the grid doesn’t. This mismatch drives congestion, curtailment,…

12 June 2026