New constraints have been imposed on large scale wind farms in the north-west Victoria as a result of efforts by the Australian Energy Market Operator to limit the size of potential “contingencies” on the grid.

AEMO currently seeks to limit a single contingency size to 600 MW, so it can make sure it has the resource at its disposal should a large coal unit or a transmission line trip.

A new assessment has discovered that the total output of renewable projects that form part of a 220 kV Generator Fast Trip Scheme amounts to up to 1,000 MW – more than it is comfortable dealing with in the event of a trip.

As a result, AEMO has imposed a new constraint – imposed from Tuesday this week – that limits the combined output of these generators – located on a troubled part of the grid known as the “rhombus of regret” to 750 MW.

Those affected are further along the 220 kV transmission line from the Waubra wind farm. The identities have not been publicly revealed but are believed to include the Crowlands, Ararat, Bulgana and Murra Warra wind farms.

AEMO says the potential constraints were agreed as part of the connection agreements for the affected projects, but says it will be temporary and will be relaxed once the new Western Renewables Link transmission line is completed.

The new constraint equation will limit the total generation output for generators associated with the GFT1 scheme (and inherent tripping of Waubra WF) to a limit of 750MW.

AEMO says the restrictions on output are likely to be limited as these wind are generally more impacted by other constraints (presumably mostly economic ones caused by negative wholesale prices), meaning that total output of the affected generators is normally below the limit, even under high wind conditions.

Want the latest clean energy news delivered straight to your inbox? Join more than 26,000 others and subscribe to our free daily newsletter.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Why an oil crisis is bad news for Australia’s biggest coal state – and how to break the cycle

One state in Australia remains particularly vulnerable to global oil shocks because it hasn't built…

13 March 2026

Energy Insiders Podcast: How the world’s fourth biggest economy plans to reach 100 pct clean energy

David Hochschild, the head of the California Energy Commission, on how the world's fourth biggest…

13 March 2026

When will the energy sector understand the National Energy Objective? When will governments enforce its intent?

Fifty years of cheap gas and electricity and intensive marketing have distorted perceptions. Every element…

13 March 2026

“It is paramount:” AEMO says system and market operator functions must be kept together

Australian Energy Market Operator says its system and market operation functions should not be separated…

13 March 2026

Powerful new rooftop solar panel promises system sizes “previously out of reach”

The Clean Energy Council has approved a new PV module with around 25 per cent…

13 March 2026

Webinar: The new era of home energy storage in Australia

An in-depth webinar exploring the next phase of residential battery storage in Australia, brought to…

13 March 2026