Wind farm gets green light for planning change, bigger turbines

Published by

The Victorian government has given the green light to a change of plans for the Woolsthorpe wind farm, in the state’s south-west, that will cut the total number of turbines installed for the project, while jacking up their size.

The state planning minister approved the change to the plans last month, giving the final go-ahead for a project that will now feature 13 turbines and have a total generation capacity of 72MW.

The previous plans for the project, which had already gained state approval, had proposed 20 turbines for the same power output, but the developers said changes in technology led to the need for a change of plans.

According to developers Enerfín, an offshoot of Spanish giant Elecnor, the wind farm will now go ahead with 13 turbines with a maximum height of 230 metres and minimum clearance of the turbine blades from ground level of 66m – up from 168m with a minimum clearance of the turbine blades from ground level of 3m.

“The previously approved turbines are no longer available by the supplier. As such, the project has been reviewed to find new turbines which would be suitable for the land,” the company says here.

“Through advances in technology, current available turbines are larger than what was previously approved. Larger turbines are however more efficient at producing power hence less turbines are required to generate the same amount of energy overall.”

In an article that is behind a paywall, the Warrnambool Standard reports that the minister’s approval of the 230-metre-tall turbines “has blindsided local councils and MPs.”

The Moyne Shire Council published a notice one year ago advising of the developers’ application to amend the Woolsthorpe permit and inviting community submissions on the proposed changes.

Council said community feedback was being sought to assist it in making a submission to the Minister on the amendment application.

According to a planning department report, the planning permit amendment application was exhibited for four weeks over September and October 2022. Forty seven submissions were received, including from seven government agencies and authorities.

The report says the majority of submissions from individuals objected to the changes, citing concerns around landscape and visual amenity, noise and dangers to local fauna.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Snowy plays down diesel allowance for Kurri Kurri, but gas pipeline problems persist

Snowy Hydro seeks to play down use of diesel at its controversial Hunter Valley power…

4 October 2024

Australia’s largest operating wind farm sends first power to Sunshine State grid

The largest operating wind farm in Australia has marked a significant milestone with the first…

4 October 2024

Renewable penetration record falls for third time this week on Australia’s main grid

Renewable records fall for the third time in five days, and likely more to follow…

4 October 2024

Macquarie’s Aula jumps on board plans to build massive wind farm in New South Wales

Aula Energy has jumped on board the plans to build a more than 600 megawatt…

4 October 2024

If Peter Dutton has a better understanding of the cost of building nuclear, then let’s see it

IEEFA's recent research on the cost of building nuclear is detailed and extensively referenced, with…

4 October 2024

“Differences of opinion:” Queensland state LNP insists it will not sign up to Dutton’s nuclear plan

David Crisafulli reminds voters that an LNP government in Queensland does not mean Peter Dutton…

4 October 2024