Wind and solar projects warned of “material” constraints in Victoria, NSW

Published by

The owners and off-takers of existing and aspiring wind and solar projects in a key part of the national grid straddling Victoria and NSW have been warned of “material” constraints to their output because of grid congestion in the area.

The Australian Energy Market Operator says the West Murray Zone (WMZ) in north-west Victoria and south-west NSW (see map below) is now effectively full because of the lack of transmission infrastructure, and new projects face delays in connection and commissioning.

The West Murray Zone – part of which has been dubbed the “rhombus of regret” in reference to the shape of its network – has emerged as a major problem area for AEMO and aspiring developers.

It has some of the best wind and solar resources in the state but, despite warnings going back more than a decade, does not have enough grid capacity.

“The capacity of the existing network to host large scale inverter-connected generation has been reached,” AEMO says in a stakeholder notice, in reference to existing and “committed” projects.

“New and existing generation across large parts of the WMZ will be materially constrained for significant periods of time pending large-scale network investments.

“This will not only restrict commercial output but may prevent or delay completion of commissioning for new projects. Connections that rely on future regulated upgrades to the network cannot be assessed until those upgrades are substantially complete.”

AEMO says there are now 21 wind and solar generators with a total capacity of 1.5GW in “full operation” in the West Murray Zone. A further eight projects with a total capacity of 1.1GW have been registered and are in the commissioning stage.

But there are also more than 25 wind and solar projects wanting to join the grid within the Western Murray Zone and currently in the application phase.

The West Murray Zone has already seen five big solar farms have their output cut in half for more than seven months due to uncontrolled “oscillations” that were finally solved through the fine-tuning of inverters.

Many other projects have been heavily delayed in connection and commissioning, as AEMO implemented a cautious “sequencing” system that processed projects one at a time. It is now looking to adopt that in other areas of the grid.

And wind and solar farms are also regularly subject to output constraints depending on the local conditions and energy flows in the grid.

It will only likely be solved by new transmission infrastructure. The new $2.3 billion transmission link from Robertstown in South Australia to Wagga Wagga in NSW will include a “spur” to Buronga and Red Cliffs, but a new transmission link within Victoria is also needed.

Ausnet is working on a proposed new 180km link from Bulgana in the north to Sydenham, near Melbourne, dubbed the Western Victoria Transmission Upgrade Project, but that has run into issues over its planned route, and a fall-out with consumer representatives who have criticised its consultation process. Even if built on time, it will not be completed until 2025.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Institutions

Recent Posts

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026

Massive wind project, with up to 280 of Australia’s biggest-ever turbines, seeks federal green tick

Plans for a potentially massive new wind farm start federal environmental assessment, proposing up to…

7 August 2026