AEMC

Wind and solar farms to be allowed to share connection points to grid

Published by

One of the many archaic rules that has caused significant blockages to proposed wind and solar projects has finally been modified in a move that will allow wind and solar farms to share connection points with others.

The changes to the Direct Connection Access regime will also make it easier for the developers of large wind and solar projects to build them in stages, without having to go back to the regulators each time they want to add new stages.

Developers such as Acciona, which is building the country’s biggest wind complex of more than 1GW at MacIntyre in Queensland, said the old regime meant it was not possible to stage projects or to effectively share dedicated connection assets between projects or stages.

“As a result, many projects are either not possible or would not be financially viable,” it wrote.

The Australian Energy Market Commission says its new rule is a “win, win” because it will make it easier for generators to share assets such as power lines.

“It is expected investment in transmission infrastructure will become more attractive to developers and investors as the new rule enables sharing of transmission assets as well as connection costs.”

It said shared access makes connection costs lower for generators than under the existing rules, and will encourage more generators to join the network.

The rules relate to transmission infrastructure built to connect a wind or solar farm – or any other generator for that matter – to the grid.

The single connection point created obstacles when multiple generators have sought to share assets, because they had to agree on one set of technical performance standards, a joint bidding strategy, share one transmission loss factor, and more.

This effectively prevented multiple parties from sharing and led to under-usage of the existing infrastructure and a disincentive to invest in new infrastructure, the AEMC said.

“With the new rule, these assets will be treated as part of the network, allowing the creation of multiple connection points so multiple generators can connect using their individual settings.”

Wind and solar developers were broadly supportive of the draft ruling, but critical of some aspects.

In response, the AEMC agreed to fast-track the implementation date of the new rule to July 22, rather than a six month delay as proposed in the draft rules.

And while it resisted calls to apply the new rule to “material additions” of transmission lines of 30kms or longer, it said shorter lines would be able to opt into the new framework.

It is not immediately clear if other concerns have been adequately addressed in the final decision.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024