Wind and solar farms to be allowed to share connection points to grid

Published by

One of the many archaic rules that has caused significant blockages to proposed wind and solar projects has finally been modified in a move that will allow wind and solar farms to share connection points with others.

The changes to the Direct Connection Access regime will also make it easier for the developers of large wind and solar projects to build them in stages, without having to go back to the regulators each time they want to add new stages.

Developers such as Acciona, which is building the country’s biggest wind complex of more than 1GW at MacIntyre in Queensland, said the old regime meant it was not possible to stage projects or to effectively share dedicated connection assets between projects or stages.

“As a result, many projects are either not possible or would not be financially viable,” it wrote.

The Australian Energy Market Commission says its new rule is a “win, win” because it will make it easier for generators to share assets such as power lines.

“It is expected investment in transmission infrastructure will become more attractive to developers and investors as the new rule enables sharing of transmission assets as well as connection costs.”

It said shared access makes connection costs lower for generators than under the existing rules, and will encourage more generators to join the network.

The rules relate to transmission infrastructure built to connect a wind or solar farm – or any other generator for that matter – to the grid.

The single connection point created obstacles when multiple generators have sought to share assets, because they had to agree on one set of technical performance standards, a joint bidding strategy, share one transmission loss factor, and more.

This effectively prevented multiple parties from sharing and led to under-usage of the existing infrastructure and a disincentive to invest in new infrastructure, the AEMC said.

“With the new rule, these assets will be treated as part of the network, allowing the creation of multiple connection points so multiple generators can connect using their individual settings.”

Wind and solar developers were broadly supportive of the draft ruling, but critical of some aspects.

In response, the AEMC agreed to fast-track the implementation date of the new rule to July 22, rather than a six month delay as proposed in the draft rules.

And while it resisted calls to apply the new rule to “material additions” of transmission lines of 30kms or longer, it said shorter lines would be able to opt into the new framework.

It is not immediately clear if other concerns have been adequately addressed in the final decision.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

World’s largest grid battery has been completed – in the oil capital of the world

The world's biggest battery energy storage system – a 7.8 gigawatt-hour behemoth – has been…

22 December 2025

Fossil gas exporters forced to give Australia “first rights” at reasonable prices – for new contracts only

Australia will keep more of its gas for the domestic market under a national reservation…

22 December 2025

Flow Power reaches financial close on its first stand-alone big battery, in Victorian coal country

Australia renewables gentailer reaches financial close on its first "battery only" project – and its largest…

22 December 2025

Snowy could emerge as the fairy godmother in race for contracts and capital to replace ageing coal clunkers

Queensland's decision to say no to renewables is bad news for some. But in NSW,…

22 December 2025

I am accused of being a global funds manager and half my age. But facts don’t matter in disinformation war

I am accused of being a global funds manager masquerading as a journalist. Facts don't…

22 December 2025

Trailblazing wind farm snapped up by Spanish renewables giant hoping to free it of grid constraints

Spanish renewables giant agrees to buy one of the heavily constrained Victorian wind farms in…

22 December 2025