Wind and solar drought: First new renewable projects join grid after six month hiatus

Published by

Over the last couple of days, wind energy has experience a short “drought” in most Australia states, but it is nothing compared to the drought of new connections and registrations of large scale wind and solar projects in the country’s main grid.

Buried in the detail of the most recent quarterly report from the Australian Energy Market Operator was this bleak assessment: “There were no projects registered and connected to the NEM (National Electricity Market)” in the first quarter of 2024.

That drought – at a time when the country needs an extra 6 GW of new capacity a year to reach its 2030 renewable energy target of 82 per cent – continued until late May when the 56 MW Crookwell 3 wind farm and the 330 MW Wellington North solar farm both entered AEMO’s management system, known as MMS, on May 21.

According to Geoff Eldridge, from data collector firm GPE NEMLog, these were the first projects entering the commissioning pipeline on Australia’s main grid since the Mannum 2 solar farm in South Australia in mid-December.

Another big project has since been added to the MMS, with the introduction of the 200 MW, two hour Western Downs battery in Queensland, located next to Neoen’s 400 MW solar farm.

According to Eldridge, it is the longest drought in new wind and solar projects since 2014, when Tony Abbott was prime minister, bent on ditching the carbon price and trying to scrap the renewable energy target, and the agencies that went with it.

Source: Geoff Eldridge, GPE NEMlog

It’s not the only piece of data that paints a grim picture of the current pace of the green energy transition in Australia, despite all the big announcements and plans for the future.

The Clean Energy Regulator says just 56 MW of new capacity was approved to generate renewable energy certificates in April, with the biggest being the 11 MW Robertson Barracks solar system in the Northern Territory, which was actually built years ago but until now was one of a handful of solar projects prevented from joining the local grid.

All of the other projects approved by the CER in April were small ground-mounted solar systems, or large rooftop solar systems, confirming the story of the last few years that it is consumers – be they household or business – that are getting on with the job of installing new capacity.

Large scale systems have been stalled by a myriad delays – in planning approvals, connections, and commissioning, and policy and market uncertainty.

The planning approval delays have been particularly bad in NSW, where IEEFA’s Amandine Denis-Ryan noted in a webinar hosted by Renew Economy this week, wind projects have taken nearly 10 years to get through the planning system.

The impact of those delays is already being felt, with the closure of the Eraring coal fired power station in NSW, at 2.88 GW the biggest in the country, put off for at least two years and possibly four because of the lack of new capacity in the grid.

Its owner Origin Energy has completed no new large scale renewable projects since flagging the early closure in early 2022, and other project developers have been unable to get going fast enough.

It’s not as though there is no queue. According to AEMO’s quarterly report, there was 41 gigawatts (GW) of new capacity progressing through the end-to-end connection process from application to commissioning at the end of the March quarter, up 70 per cent from a year earlier.

But the total number of “proposed projects”, including those who have yet to enter the connection process, totals more than 250 GW, according to AEMO’s most recent Generation Information data.

That pent up demand was reflected in the 19 GW of applications for just 600 MW of four-hour storage capacity on offer in Victoria and South Australia as part of the new Capacity Investment Scheme.

It is hoped that the CIS can, in fact, unlock that pipeline and open the doors for at least some of the projects queued at the gate. Its first tender of 6 GW of new wind and solar is opening this month, and will be followed by similar sized tenders later this year and next.

In all, the federal government is targeting 23 GW of new wind and solar capacity and 9 GW of storage capacity to be tendered so they can be built by 2030. Analysts such as Denis-Ryan say that target for wind and solar should be lifted from 23 GW to 36 GW to ensure that the renewable target is met.

But one of the issues is that new developments – with the exception of some of the largely “behind the metre” projects for large customers, such as the gigawatt scale wind and solar deals proposed by mining giants Rio Tinto for its smelters and refiners – are now captive to the CIS process.

Indeed, it has been argued that the CIS process itself has slowed recent developments because potential off-takers and developers have waited to see what they can achieve in that auction process before moving forward with their projects.

The federal Coalition, on the other hand, wants to scrap it all – demanding that all new wind and solar projects be brought to a halt, and has even threatened to tear up contracts with the federal government.

It has made clear it thinks coal fired power stations should be kept open until the first nuclear plants can be delivered, likely to be in the early 2040s. Most in the energy industry point out that would be a disaster for emissions, costs, and grid reliability.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Featured

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024