The 130MW Glenrowan solar farm in Victoria is now fully commissioned, with construction through to going live taking just 12 months. 

The news was announced in a LinkedIn post by UGL renewable energy connections manager James Brennan, who said hold point testing was complete and the solar farm is now operating at “full unconstrained capacity.”

“Another very successful EPC project by UGL New Energy, also being the 3rd major utility scale solar project completing commissioning by our team within just 12 months!” Brennan wrote. 

Cimic Group company Pacific Partnerships energised the Glenrowan Solar Farm in late November last year and began exporting electricity to the national grid in December.  It is still waiting on AEMO’s final approval before officially launching.

It planned to ramp up to full production by the end of March 2024, to supply some 45,000 homes.

Located on 245 hectares in Victoria’s proposed North East Renewable Energy Zone (REZ), the solar farm has grid connection and service agreements with the Victorian transmission network operator AusNet and the Australian Energy Market Operator (AEMO).

The Glenrowan Solar Farm is contracted through a 10-year power purchase agreement with the Victorian Government.

Just five days ago UGL said it was “steadily making strides towards completion in early 2024” and noted the volume of work completed in the last 12 months, including 32,000 piles laid for 226,000 solar panels, and 2,150 trackers.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Recent Posts

Second wave of big batteries will eat the dinner of fossil fuels, forcing some coal generators to close

The current second wave of big battery projects will kill the economics of most coal…

5 September 2026

Climate Authority’s “misinformation” report hit a nerve at News Corp for a reason

Few organisations have so consistently campaigned to stymie climate action – possibly anywhere on the…

4 September 2026

Energy Insiders: Zero carbon heat, Australia’s next big challenge

Tom Geiser from Good Heat on the technologies to provide carbon-free industrial heat. Plus: LNP's…

4 September 2026

Australia’s climate hypocrisy on show as world braces for global warming “overshoot”

Days apart, one Australian minister called for reduced dependence on fossil fuels, while another literally…

4 September 2026

Gigawatt-hour battery plan edges closer to construction as Swiss giant takes full ownership of site

Swiss storage giant completes purchase of the project site for big four-hour battery, setting a…

4 September 2026

“Golden turbine” complete, in huge milestone at rare state-owned wind farm

Installation of the "golden" turbine is being hailed as a "huge milestone" for a wind…

4 September 2026