After months of waiting, the turbines are now spinning at Windlab’s world-leading Kennedy solar-wind-battery project in north Queensland.
The company, which faced delays of more than six months from completion of construction before it could connect to the grid – as well as other issues, including flooding – tweeted on Tuesday that the first generating had finally occurred.
The unique energy hub – the first in the world to combine all three technologies on a major grid – will feature 43MW of wind, 15MW of solar and a 4MW/4MWh Tesla battery. Full commissioning is expected by the end of this quarter. A planned expansion will depend on enhanced networks.
Fate of huge wind farm proposed off north-west Tasmania remains stuck in limbo, after a…
Tasmania’s first renewable hydrogen production plant launches north of Hobart, where it will produce 262kg…
One of the winners of the federal government's first giant wind and solar auction is…
A UK company says its newly-developed, manganese-rich cathode material could increase battery energy density by…
Battery expert Iola Hughes from Rho Motion on the latest trends, developments and date on…
It might have much fewer grid-connected renewable assets than other states, but February data once…