Turbines and transmission towers up and concrete foundations poured at rare state-owned wind farm

Published by

The last of the concrete foundations have been poured for the 46 turbines that will make up the 285 megawatt Lotus Creek wind farm in central Queensland, in what has been described as a “huge few weeks of milestones” for the state government-owned project.

Andrew Wilson, the head of renewables and firming at Queensland utility CS Energy says the wind farm has started receiving turbine component deliveries and has completed “tower pre-installation” at the first two turbines.

“We’ve also poured the last of 46 foundations, delivered the 2x main transformers plus switch room and control room buildings, passed the halfway point of underground cabling, and erected the last of 30 transmission line towers,” said Wilson on LinkedIn on Monday.

CS Energy bought the $1.3 billion Lotus Creek wind farm in August 2024 from Danish giant Copenhagen Infrastructure Partners, marking the first 100 per cent publicly owned wind farm to reach construction phase under the former Labor government’s Queensland Energy and Jobs Plan.

So far, the project has remained publicly owned under the current LNP government, although as Renew Economy reported over the weekend, this might not be the case for long.

CS Energy sold a half share in the under construction 228 MW Boulder Creek wind project to joint venture partner Aula Energy in a deal quietly announced on June 26, in the latest in a series of moves that has seen Queensland state-owned utilities withdraw from equity positions in key renewable projects.

And the AFR has reported that CS Energy is seeking investors in Lotus Creek.

Another state owned utility, Stanwell, in February announced its decision to sell its option over a half share in the 436 MW Tarong West wind project to Innergreen, a private investor that will now partner RES in its development. Stanwell still has an option to buy the output of Tarong West.

For now, however, Lotus Creek continues to make progress under CS Energy’s ownership.

“These milestone are a testament to the hard work and talents of a large and diverse team across our Principal Contractors and their subcontractors – incredibly proud to get to work with them on this project,” Wilson said.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, you can click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026