Turbine shut downs at Victoria wind farm part of “staged maintenance,” says Squadron

Published by

Squadron Energy has confirmed that a number of turbines at the 226 megawatt (MW) Murra Warra 1 wind farm in north-western Victoria are temporarily out of action, as part of “staged maintenance” to replace failed bearings.

A spokesperson for Squadron said on Wednesday that work on a bearing refurbishment program on around half of the turbines at Murra Warra started recently and is expected to be completed next year.

Squadron says the works are limited to 32 of the project’s 61 Senvion turbines, with 15 currently switched off to undergo maintenance – half of the number claimed in local media reports on Wednesday.

“The wind farm continues to generate power, with staged maintenance taking place to replace certain failed bearings, and a number of turbines have already returned to service,” the spokesperson said in an emailed statement.

“Wind turbines are operational for 30 years or longer. As with a car or any other large complex machine, there is ongoing maintenance and some parts may warrant refurbishment.”

The Murra Warra wind farm – which totals 429 MW with the addition of the 209 MW stage 2 project – is a significant project for Victoria, delivering electricity under long-term contracts to Telstra, and a consortium of customers that includes ANZ, Coca Cola Amatil and the University of Melbourne, as well as Monash University.

Stage one of the Murra Warra project north of Horsham first started exporting electricity to the grid in early 2019, when it was under the ownership of Macquarie Group and renewable energy developer RES Australia.

Murra Warra 1 and 2 were acquired by Squadron Energy as part of the CWP Renewables sale by Partners Group.

The wind turbines for Murra Warra 1 were supplied by the now defunct German wind turbine manufacturer Senvion, which had put itself into administration by the time Murra Warra 1 started powering up.

By the end of 2019, Senvion had sold its European service fleet to Siemens Gamesa. Only the Indian division of the company – Senvion India – remains, after it was acquired by Saudi Arabian company, Alfanar, in 2021.

  • In the case of the Murra Warra turbines, the German manufactured bearings are being transported to Melbourne for refurbishment at a specialised facility.

Squadron says the maintenance works do not affect any of the turbines at Murra Warra 2.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Gina Rinehart-backed, geothermal powered “pit to battery” project marks key milestone

ASX-listed Vulcan Energy Resources is marking a milestone in developing a sustainable EV battery supply…

14 January 2025

Compressed air storage pioneer secures billion-dollar loan to deliver 8 hours back-up to California grid

The outgoing Biden Administration commits to help fund the deployment of a novel long-duration energy…

14 January 2025

Peter Dutton’s “always on” nuclear power is about as reliable as wind and solar – during a renewables drought

New analysis finds modern nuclear power plants are, on balance, about as "always on" as…

14 January 2025

Much of Australia has the same climate as LA. When it comes to bushfires, that doesn’t bode well

The catastrophic fires burning in one of the most densely populated parts of the United…

13 January 2025

Daytime wholesale power prices are heading to zero – isn’t that good news?

A new low proposed for solar feed-in tariffs is bound to spark consumer outrage and…

13 January 2025

Big win for Fortescue as massive 800 MW wind farm gets federal green light

Huge Fortsecue-owned wind farm wins federal environmental approval, subject to conditions, to go ahead as…

13 January 2025