Transmission

Transgrid chooses lower cost option to connect NSW load centres with regional renewables

Published by

Plans for a “ring” of new transmission lines to link New South Wales’ coastal load centres with the state’s various renewable energy zones and with other major network upgrades are on public display via Transgrid.

Transgrid has published the preparatory report for the Reinforcing Sydney, Newcastle and Wollongong Supply (RSNWS), aka the Southern Ring, as it races to prepare the state’s grid for the exit of coal and build-out of renewables.

The Southern Ring aims to link the flows from Project EnergyConnect, HumeLink and VNI West via new 500 kV transmission lines from Bannaby into the Sydney western suburbs connecting to the ‘inner’ 500 kV system.

Transgrid has chosen its preferred route for Sydney Southern Ring, at a cost of roughly $1.5 billion, in preference to an alternative that was likely to cost nearly twice that much.

The project must still proceed through the Australian Energy Market Operator’s Integrated System Plan and RIT-T framework and Transgrid says it is important to secure easements around the new airport in western Sydney.

“The geographic dispersion of renewable generators …and the required growth of renewables to reliably and securely transition the NSW transmission network to net zero emission by 2050, necessitates new transmission infrastructure to efficiently transfer many GW of power across hundreds of kilometres,” the report says.

Source: Transgrid. Please click to expand.

“To reach these new renewable generators, we need new transmission connections from REZs to the 500 kV Energy Superhighway transmission backbone supplying SNW via a 500 kV ring, providing efficient security of supply from both the north and the south.”

Transgrid says that for an area that accounts for around three-quarters of the state’s electricity demand – and with “no plans for new baseload generation” – supply will need to come from generation from outside the area.

And it says that if NSW coal generation retires earlier than expected, the state may need to “bring forward the planned in-service dates” of the Sydney Ring transmission projects to “reduce the risk of load shedding in Sydney, Newcastle and Wollongong.

New South Wales has a huge task ahead of it to build enough firmed renewable energy generation in time to wean the state from fossil fuels – and AEMO has warned that this can’t happen without the transmission task being completed first.

Transgrid earlier this month revealed it had finalised a deal to secure critical transmission equipment as it prepares to do its part in delivering national priority grid projects.

The $100 million contract with ZTT Australia has secured supply of 17,500km of high voltage conductors – enough to stretch from Sydney to Dublin, Transgrid said. A separate contract with another Australian company would secure supply of other locally-produced conductor elements.

Transgrid says the “bundling procurement” plan will save it up to $500 million on the hefty costs of its for major projects HumeLink, VNI West and EnergyConnect.

The stockpiling program – supported by $385 million federal funding from the Rewiring the Nation program – is also allowing the network company to purchase materials like substation equipment, earlier and at a lower cost, Transgrid says.

“We continue to build our global supply chain to secure the specialised kit needed to build the future clean energy grid and ensure competitive and efficient delivery of the Federal Government’s energy plans,” said CEO Brett Redman.

“It’s also reducing risk as we compete with other energy companies and nations to secure critical, large-scale equipment, materials and skilled labour to deliver the projects Australia needs,” added Transgrid executive general manager of delivery, Craig Stallan.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Neighbours of giant wind project offered up to $100m in unique deal that could shape design

Near neighbours of one of the country's biggest wind projects are being given the opportunity…

31 January 2025

Farmers offered $300m in discount loans for solar, batteries, EVs, seaweed and windbreaks

Farmers offered up to $300 million of discount loans to help efforts to cut emissions,…

31 January 2025

Biggest vanadium flow battery in Australia promised for ailing Kalgoorlie grid

A 500 MWh vanadium flow battery - the biggest in Australia - has been promised…

30 January 2025

Big batteries cash in as they charge past gas to become second biggest player in evening peaks

The growth of big battery projects - fuelled by falling costs and growing needs -…

30 January 2025

Australian university joins $230m future materials project backed by mining giant

A $230 million project investigating ways to make extracting future materials more sustainable will bring…

30 January 2025

“Like a Corolla with racing tyres:” Why Australia’s outdated electricity market fails renewables

Australia’s electricity market is old, outdated and not doing enough to drive investment in the…

30 January 2025