Solar

Top End puts out call for 100MW of solar, but they must come with grid forming batteries

Published by

The Northern Territory government energy utility Jacana has opened its tender for up to 100MW of large scale solar farms, with the specific requirement that each of the three solar projects come with their own grid forming batteries “so the network doesn’t fall over.”

The tender seeks three separate solar projects between 30MW and 35MW each, but because of the strict dispatch rules on the local grid, each will have to come with their own 10MW/10MWh battery.

These big batteries will have to be armed with “grid forming” inverters, rather than “grid following” inverters, which means that they need to have the ability to set their own path in the grid and provide key system services.

Jacana has already contracted three big solar farms in the NT, but two of these have not started generating because they do not have battery storage and cannot comply with the local grid requirements which require them to accurately forecast their output 24 hours in advance.

The owners of those solar farms argue that those rules were introduced after their won their contracts to build their solar projects, and they are contesting the rules in court. A third solar farm, at Katherine, has started generating limited amounts because it has a small battery storage system.

Jacana, however, is ploughing ahead with a new tender that explicit outlines the battery storage requirements and dispatch rules. It hopes to have the new solar farms, with batteries, on line in 2027 – still four years away and says it will contribute around 15 per cent of the territory’s 50 per cent renewable target for 2030.

“We are a very small network,” Luke Stapleton from Power and Water Corp, which sets the rules of the local grid, told a webinar explaining the tender last week. “They are there as a requirement so the network won’t fall over.”

The tender for power purchase contracts formally opened this week. It is seeking initial responses by the end of September. The successful projects are also being encouraged to locate within designated renewable energy hubs.

The Darwin-Katherine energy system has relatively low demand and features large amounts of rooftop solar, which is making inroads into the gas generators that continue to dominate the system. A 35MW one hour battery is being built in Darwin to allow less gas units to keep running as back up.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Energy Insiders Podcast: How industry, AI and data centres are reshaping demand

GridBeyond CEO Michael Phelan on how industrial loads and data centres are being orchestrated by…

20 February 2026

Australian home battery upstart banks “strategic investment” towards manufacturing plans

Perth-based energy storage and off-grid energy system specialist secures a new private equity investor to…

20 February 2026

Can all solar homes become smart energy hubs? On paper – absolutely! IRL, a few hurdles remain

A South Australian trial to turn homes into grid-responsive energy hubs is now 100 households…

20 February 2026

Plan for Australia’s biggest solar-battery hybrid, with eight hours storage, get federal green tick

Plans for one of Australia's biggest solar-battery hybrid projects have been waved through the federal…

20 February 2026

AI + energy: Monster child of Origin and Facebook – or a smart, decentralised grid?

Will AI’s growing role in the grid democratise clean energy, or simply shift power from…

20 February 2026

Transmission “legacy:” State launches CopperString community benefits fund

A community benefits find will share $50 million across a series of “legacy projects” for…

19 February 2026