Tilt Renewables output hit by system strength cutbacks and low wind speed

Published by

Wind farm owner and developer Tilt Renewables has revealed its June quarter output has been hit by lower than average wind speeds and curtailment of its Snowtown 1 wind farm in South Australia because of system strength restrictions.

The output of its existing wind farms – not including the Snowtown 2 wind farm recently sold for $1 billion – was down more than 12 per cent on the same period last year, and more than 10 per cent below expectations.

It says this was driven primarily by wind speeds below long term forecast levels and the curtailment of the 101MW Snowtown 1 wind farm due to the South Australian System Strength constraint imposed by the Australian Energy Market Operator. It says this amounted to 4 gigawatt hours during the quarter.

Overall production was 23 per cent higher at 347GWh thanks to an additional 81GWh of output from the newly connected but only partially commissioned 336MW Dundonnell Wind Farm in Victoria.

Red bar in June quarter shows fall in output from existing wind farms, with striped red showing addition of newly connected Dundonnell.

Dundonnell is so far operating at 116MW of capacity, but Tilt revealed last week that it had been told by AEMO that commissioning of the rest of the wind farm’s capacity would be delayed due to unspecified network issues. Tilt has lamented the lack of clarity on the issue from AEMO and says it has followed its connection agreement to the letter.

The delay in full commissioning has forced the company to write down its full year profit predictions to a range of $65 million to $80 million, assuming average wind conditions, from its previous forecast (made less than two months ago) of a profit in the range of $80 million to $95 million.

Snowtown 1 sells its output into the spot market, while Dundonnell has 93 per cent of its full output contracted to the Victoria government, Snowy Hydro and Aldi, although it will initially sell the output at spot prices until the PPAs come into effect. It says it cannot now say with certainty when it will reach full commissioning for Dundonnell even though all 80 turbines are now erected.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Recent Posts

“Playing catch-up:” Sunshot targets cheaper construction in quest for ultra-low cost solar

Arena says the pursuit of ultra-low cost solar is making "good progress" at the panel…

15 October 2026

Long lead times for syncons, gas turbines complicate energy market transition, major supplier says

Gas turbines aren't the only large equipment with long lead times.

14 October 2026

Why the old tradie business model won’t deliver all-electric homes | SwitchedOn Australia

All Electric Homes founder Trent Jones warns that a shortage of skilled tradies, fragmented business…

14 October 2026

Webinar: Hard-earned lessons for BESS operators – warranties, diagnostics, and contract design

For asset owners, buyers, managers and O&M teams, the webinar will cover performance metrics, service…

14 October 2026

Commissioning starts on what will be state’s biggest battery – but not for long

Less than two years after starting construction, four-hour big battery energy storage system powers up…

14 October 2026

“Stunning example of market working:” Households embrace free power offer, causing major spike in demand

Fascinating chart backs up AEMO chief's observation that people are piling in on the offer…

14 October 2026