“The only one in Australia:” First of its kind eight-hour battery with rapid charging formally opened

Published by

A first of its kind eight-hour battery, with special permission to charge in half the time, has been formally opened in the south-west of NSW, one of the first of nearly 100 renewable and storage projects benefitting from state and federal underwriting schemes.

The 50 megawatt (MW) and 400 megawatt hour (MWh) Limondale battery was the first project to win a long duration tender, an underwriting mechanism that had been expected to be dominated by pumped hydro.

But it won on lower costs and the success of this and other eight-hour batteries has helped change much of the thinking about storage in Australia’s main grids, relegating pumped hydro other technologies that are being hit hard by higher civil construction costs to “deep” and “seasonal” storage.

The Limondale battery – near Balranald and next to the 314 MW solar farm of the same name – has been delivered by German energy giant RWE, using 144 Tesla Megapacks. It has already been commissioned, as we reported here.

“It’s exciting to cut the ribbon on this Australian-first battery, which will get more renewable energy into the grid, placing downward pressure on bills,” said NSW minister for Energy and Climate Change, Penny Sharpe.

“Batteries like this one mean we don’t waste an electron of solar and can power the state with renewables.”

It is believed to be the first battery in Australia that has been allowed “asymmetric” registrations – meaning it is permitted to charge at a rate of 100 MW, although its discharge is limited to 50 MW as per the requirements of the long duration storage contract.

“The battery must be registered as an eight hour dispatchable asset on the ground,” Tesla’s head of development Shane Bannister told the Australian Energy Week forum in Melbourne on Wednesday.

“The good thing is it doesn’t say anything about how it needs to be registered to the charge side, so for Limondale it’s an asymmetrical registration with AEMO, which I’m pretty sure is the only one in Australia.

“So it’s registered at 50 MW discharge and 100 MW from the charge side, that’s pretty unique, it allows that asset to now charge at full power, being 100 megawatts for four hours.

“Now, if you’re wondering why that’s important, more often than not, even with the suppression of the (solar) duck curve that we’ve seen from the home battery subsidy scheme and from other utility scale factors, that window of when you really want to charge your asset is kind of four hours long.”

See this story for a further explanation: What’s the difference between a four-hour battery and an eight-hour battery? Not a lot, it turns out

RWE CEO Daniel Belton described the asset as “one of Australia’s most significant battery storage projects” and a “major step forward for long-duration energy storage” in the country’s main grid.

“Limondale BESS strengthens grid stability, supports energy security and enables greater integration and efficient use of renewable energy across the network,” he said.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Concrete foundations completed for all 18 turbines at first and smallest wind farm to begin construction this year

All 18 of the concrete turbine foundations have been poured at the first wind farm…

24 October 2026

Snowy profits steady amid pumped hydro strains, while CEO Barnes sees his take-home benefits sink below $2 million

Snowy Hydro reports a modest uptake in profits in the year to June 2026 while…

23 October 2026

“Reset 3.0” doesn’t answer the biggest questions about Snowy’s $25 billion-plus pumped hydro gamble

Engineering marvel or financial folly? We've been here before - a cost blowout and a…

23 October 2026

Energy Insiders Podcast: Fast lane to electric, and Snowy blowouts

Bruce Hardy from the Energy Futures Foundation on the fast track to electric transport, and…

23 October 2026

Energy efficiency has finally become an election talking point, but for all the wrong reasons

State Liberals and mainstream media are keen to criticise Victoria's popular energy upgrades scheme, but…

23 October 2026

“What’s better, gas or starvation?” Pipeline giant’s extraordinary response to Beetaloo critics

At a contentious annual general meeting, activist shareholders have questioned the viability of future greenfield…

23 October 2026