Renewables

Thailand switches on 45MW floating solar plant, plans for 15 more

Published by

One of the world’s largest hybrid floating solar arrays has officially begun commercial operation on a hydropower dam in the east of Thailand, with plans for 15 more such projects to come, totalling 2,725MW across the country.

The Electricity Generating Authority of Thailand (EGAT) said this week that the 45MW Hydro-Floating Solar Hybrid Project at Sirindhorn Dam began had been switched on at the end of October atop Sirindhorn Dam in Thailand’s Ubon Ratchatani Province.

It is billed as a “hybrid” project as it can not only produce electricity from solar panels during the day but also hydropower from the existing dam.

Image: EGAT
Image: EGAT

Egat has claimed the Thai floating PV project as the world’s largest floating solar and hydro plant, which it well may be. On floating solar alone, however, there is a bigger 60MW array on the Tengeh Reservoir in Singapore that was recently completed.

And in Indonesia, a project that will top them all is in the works, with a 2,200MW floating solar farm, paired with more than 4,000MWh of energy storage, recently approved for construction on a reservoir on Batam Island.

In Thailand, development of the Sirindhorn Dam has sought to go beyond power generation by serving as a potential tourist attraction in the Ubon Ratchathani Province, while also creating jobs and income for the community.

Worth noting is that the “tourist” aspect of the dam is not limited to a dim hope that renewable energy enthusiasts will begin flocking to the area, but as can be seen in the photos below, the area has been developed as a must-see destination for visitors to Thailand.

Image source:www.egat.co.th
Image source:www.egat.co.th

According to EGAT, the 145,000 solar panels have been arranged into seven arrays that cover less than 1% of the entire reservoir. The floating solar plant also uses the dam’s existing transmission system and electrical equipment, helping to reduce overall costs.

The Electricity Generating Authority of Thailand has decided to move ahead with a larger 15-site portfolio of floating solar projects atop EGAT dams which will reach a total capacity of 2,725MW.

This new portfolio of projects will kick off with a 24MW floating solar project atop the Ubol Ratana Dam in the Khon Kaen Province of north-east Thailand.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Fast lane to electric, and Snowy blowouts | Energy Insiders

Bruce Hardy from the Energy Futures Foundation on the fast track to electric transport, and…

29 October 2026

WA renewable energy target sends investors the signal they need – at a critical time

A strong state target for renewables sends the message that WA is a stable market.…

29 October 2026

Ratings system designed to restore trust in wind and solar developers goes live, with first batch scoring well

Online rating tool that ranks renewable energy developers and transmission companies against seven key criteria,…

29 October 2026

“Anti-renewables populism is the largest unpriced risk:” But poll data shows support is growing, even in hot zones

Polling by Squadron Energy finds higher support than expected in western Victoria and central NSW,…

29 October 2026

LNP hits brakes on pumped hydro project, spooked by Snowy 2.0 cost blowout

Contracting for huge pumped hydro project has reportedly been suspended by the state treasurer and…

29 October 2026

Snowy 2.0: The potentially $50 billion shambles that really needs a proper cost-benefit analysis

Even now, with $12 billion sunk, stopping Snowy 2.0 may be the least-worst decision. It…

29 October 2026