Tesla unveils 18.2MW big battery in Belgium

Published by

Tesla has unveiled its latest large-scale battery project, this time in Europe, where an 18.2MW collection of 140 Powerpacks and inverters has been connected to the grid in Terhills, Belgium

The project – which Tesla says took six months to complete from inception to operation, with the battery installation itself taking about five weeks – was unveiled on Tuesday afternoon (Australian time) by the California based company via its various social media channels.

According to ReNews, the €11 million storage array, located at the Terhills resort, is pooled with a mix of demand response assets from industrial and commercial consumers, and is one of the largest batteries in Europe contributing to the grid.

While a fraction of the size of the 100MW Hornsdale Power Reserve “big battery” in South Australia, the Belgian battery bank will be used for similar “grid balancing” purposes on the European grid – as the video below explains.

It will combine with various demand response services to provide around 32MW of grid capacity. The number of Powerwalls – 140 – suggests storage capacity of 28MWh, but this will depend on the final configuration.

If it’s anywhere near as effective as its SA counterpart, it should do a pretty good job.

As RenewEconomy reported on Friday, new data from McKinsey and Co – presented at Australian Energy Week – shows that the Hornsdale Power Reserve has taken a 55 per cent share in the state’s frequency and ancillary services market, and lowered prices in that market by 90 per cent, since being switched on.

 

Meanwhile, in Australia, work has begun on the Bulgana Renewable Energy Hub in Victoria which will see the state’s first combine wind farm and battery storage, including a 20MW/34MWh Tesla battery.

Tesla is also working on another large-scale battery storage project – the Gannawarra Energy Storage System, which will add a 25MW/50MWh Powerpack battery system to Victoria’s biggest solar farm, the 50MW Ganawarra project in the state’s north-west.

And earlier this month, Tesla CEO and chief visionary Elon Musk let slip about a soon-to-be announced new big battery project that would dwarf the SA installation.

Musk said the new project would be announced within a few months – he did not say where it will be installed – and that at 1GWh it would would be eight times bigger than Hornsdale.

“The utilities have really loved the battery pack. I feel confident that we will be able to announce a deal at the gigawatt hour scale within a matter of months,” Musk told a conference call following the release of the company’s March quarter results.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024