Tesla takes control as Bouldercombe battery gets green light just six weeks after Megapack fire

Published by

The Bouldercombe big battery in Queensland has been given the all clear to operate at full capacity by the Australian Energy Market Operator after successfully completing its commissioning process, just six weeks after a fire erupted in one of its Tesla Megapack modules.

The 50 MW, two hour (100 MWh) Bouldercombe battery will be the second big battery to be switched on in the Queensland grid, following the 100 MW, 150 MWh Wandoan South battery that joined the grid in 2022. But it will be followed by many others.

Genex Power said on Friday that the project will initially operate with only 38 of its 40 Megapack modules, with Tesla due to replace two modules by early December, including the one damaged by the fire on September 27, and a neighbouring module that could have been impacted by the heat of the fire.

The battery will be operated by Tesla – using its “autobidder” system – and the two companies will share the profits under a unique agreement that was first announced early last year.

“The completion of construction and commencement of operations at our 50MW/100MWh Bouldercombe Battery Project is an exciting milestone for Genex,” CEO Craig Francis said in a statement.

“Bouldercombe is our first battery energy storage project, and after the fire event in late September, delivering it with only a modest delay and within budget is a fantastic outcome for Genex and its partners.”

Francis said the timing of the commissioning “could not be better” as the battery will plug into the newly created Fast Frequency Response ancillary services market, which commenced early last month, and is well placed to respond to the stresses on the grid anticipated from the looming El Nino summer.

“The commencement of operations will mark the next step-change in revenues and cash flows for Genex, and we are also extremely pleased that Bouldercombe will be able to play its part in supporting the Queensland energy system over this period.”

Genex is also working on its much bigger storage project, the Kidston pumped hydro scheme, which is sized at 250 MW with eight hours storage (2,000 MWh) and is due to be complete by the end of next year.

That project, remarkably for a civil construction project, is largely within budget and timeframes, and recently completed its main tunnelling. It is being built in and around a former open pit gold mine, and Genex is looking to add a 258 MW wind farm to the precinct that already features the 50 MW Kidston solar farm.

Genex is also embarking on what could be the biggest solar project on the country’s main grid after landing a 25-year contract for 337 MW of solar capacity at Bulli Creek with Andrew Forrest’s Fortescue Metals for its green hydrogen and green ammonia plans at Gibson Island in the port of Brisbane.

The company is currently looking for more customers, but says the solar project will be sized at a minimum 450 WM and possible 750 MW. Large battery storage facilities will likely follow at the same site.

The Bouldercombe battery will deliver a significant uplift in revenue for Genex, and is expected to bring in about $15 million a year to Genex under its revenue sharing deal with Tesla, although this will depend on the volatility of the market.

That will effectively more than double its current income which is sourced from its two operating solar farms at Kidston and Jemalong, both of which are 50MW.

“It will be great to be able to tap into some of the upside of the market,” Francis told RenewEconomy in the latest episode of the weekly Energy Insiders podcast.

See also RenewEconomy’s Big Battery Storage Map of Australia

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024