Tesla big battery at Lake Bonney wind farm faces connection delays

Published by

The latest Tesla big battery to be installed in Australia’s main grid – at the Lake Bonney wind farm in South Australia – is facing connection delays and is now not likely to be completed until the September quarter.

Infigen Energy, which is installing the 25MW/52MWh battery, using Tesla Powerpacks, at the 275MW Lake Bonney wind farm, had expected the first stage of the battery to be completed in February and the second stage in May.

But in its first quarter production report, released last week, Infigen reveals that while the “physical installation” of the $38 million battery is substantially complete, including the inverters and related balance of plant, connection issues are still being worked through.

“Studies are continuing between Infigen, the market operator and the network service provider in relation to finalising connection and access to the electricity grid,” Infigen says in its statement.

“Based on progress to date, full commercial operation of the BESS is now expected in Q1 FY20.” Which is the September quarter. As recently as February, the company said the battery should be commissioned in the current quarter.

Infigen is not the only company facing delays due to connection issues with either the market operator, the local networks service provider, or both. Connection costs and delays have caused mayhem in certain parts of the market, causing cost blowouts in a number of projects across the country.

Cost over-runs – not always due to connection issues – have claimed leading contracting firm RCR Tomlinson, which is now liquidated, and more recently Tempo Australia, which has suspended its shares because of potential cost blowouts at the Cohuna solar project in Victoria.

The experience with new batteries is completely different to the first Tesla big battery, at the Hornsdale Power Reserve, which was delivered in less than 100 days – as promised by Tesla CEO Elon Musk.

However, most recent battery installations have faced short or longer delays, for a variety of different reasons. These include the Dalrymple North battery in South Australia, and the two batteries in Victoria, at Ballarat and Gannawarra.

Tesla has battery installations complete or under construction, or in commissioning, at Hornsdale, Gannawarra, Lake Bonney, Bulgana and Kennedy.

The Lake Bonney battery is receiving $5 million in funding from each of the Australian Renewable Energy Agency and the South Australia government.

The battery will provide frequency and ancillary services to the grid, as well as storing energy from the wind farm, allowing Infigen to “firm” its supply contracts with commercial and industrial customers.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

“They solve the problem:” Leading storage developer says battery costs have plunged 70 pct in two years

Owner of Australia's most successful big battery developer says storage costs have plunge 65-70 pct…

10 May 2026

Landholder-led 4-hour big battery gets federal environmental all-clear in just over four weeks

A big battery project being proposed for construction by a group of farming landholders and…

8 May 2026

“I thought this was impossible:” Fortescue green grid rides through transmission failure with no fossil fuels

Fortescue's green grid rides through bushfire-caused transmission failure with just solar and batteries and no…

8 May 2026

Fund nears financial close for wind and storage projects, with Victoria Big Battery extension first to go

Listed fund hopes to press go on its first big wind and storage projects soon,…

8 May 2026

“Definitely not good policy:” Experts skewer LNP plan to pause major transmission upgrades

Opposition plan to review state transmission roadmap and pause major network upgrades has been called…

8 May 2026

“Completely overwhelmed” Attenborough feted on 100th birthday, new wasp species named after him

A new species of wasp has been named after Sir David Attenborough as the naturalist…

8 May 2026