Tasmania’s Granville Harbour wind farm now sending power to the grid

Published by

Tasmania’s 112MW Granville Harbour wind farm has started sending power to the grid – although just a fraction of the one-third increase to the state’s wind power capacity it will ultimately deliver.

As you can see on the chart below supplied by Paul McArdle from Global Roam, the providers of our popular NEM-Watch widget, first generation for the wind farm was recorded on February 1, and has gradually increased over the month to around 7MW on Tuesday.

The $280 million project is being developed by developers Palisade Investment Partners and by Royce Smith, whose cattle grazing land on Tasmania’s west coast is hosting the wind farm.

The first of the project’s 31 turbines was erected in late November of 2019, after what Smith described as a “long and challenging process” stretched across 10 years.

The project was initially being developed by Westcoast Wind, which was bought out by Palisade in February 2018, some months after the two companies negotiated a long-term PPA for the wind farm’s output with Hydro Tasmania. It reached financial close in July of 2018, after a $59 million investment from the Clean Energy Finance Corporation.

As we reported here in November, the project is on track to be completed entirely by mid-2020 and, once operational, will generate enough power to supply around 46,000 Tasmanian homes.

Hydro Tasmania says Granville Harbour will contribute to its plans to double the Apple Isle’s renewable energy capacity and make it the Battery of the Nation.
Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Billboard blunders reveal dangerous double standards on climate change

When the words "climate change" can have your ad refused, but fossil fuel companies can…

9 March 2025

Abbott’s legacy, Trump’s playbook: Is the LNP planning science suppression 2.0?

The federal Coalition has made it clear it will not move on climate policies. Will…

9 March 2025

Federal and state governments give priority to 56 wind, solar, battery and transmission projects

New priority list includes 24 transmission projects, 16 GW of wind and solar projects, and…

9 March 2025

Plibersek delays call on controversial Tasmania wind project again, as local division deepens

Fate of huge wind farm proposed off north-west Tasmania remains stuck in limbo, after a…

7 March 2025

Green hydrogen production plant taps 100 pct renewable grid using cutting edge electrolyser

Tasmania’s first renewable hydrogen production plant launches north of Hobart, where it will produce 262kg…

7 March 2025

Andrew Forrest-backed wind and battery project could be first to drop off federal CIS winners list

One of the winners of the federal government's first giant wind and solar auction is…

7 March 2025