Tasmania terminates contract with Basslink, as legal fight continues

Published by

The Tasmanian government has assured that the state’s energy security is “stronger than ever” after effectively binning its commercial contract with the company that operates the Basslink undersea cable that links Tasmania’s grid to the Australian mainland.

Tasmania energy minister Guy Barnett said on Thursday that the government and state-owned utility Hydro Tasmania had taken “another step” towards protecting their legal rights, by terminating the Basslink Services Agreement (BSA).

The move is the latest in a years-long dispute between the two parties, that started when the Tasmanian state government sued Basslink for damages over the long interconnector outage that hit the island in 2015.

Barnett said that the termination of the commercial contract would not affect the state’s energy security, which remained on “firm footing” thanks to strong hydro storage levels and the Cattle Hill and Granville Harbour wind farms.

The undersea cable, meanwhile, would remain in service while negotiations continued with Basslink’s administrators “on alternative commercial arrangements, suitable for the receivership period,” Barnett said.

In a separate statement, Hydro Tasmania said it had made “a good faith offer” for an interim arrangement, under which key elements of the BSA would be put back in place for one more month while the parties discussed possible alternative arrangements.

As RenewEconomy has reported, the months-long failure of Basslink back in 2015-2016 was part of a series of unfortunate events spurred by Tasmania’s driest Spring on record, which depleted the state’s hydro electricity generation capacity – the state’s usual source of reliable renewable power.

Tasmania responded by starting to import more electricity from Victoria, until the link to the mainland failed, taking it out of action for months and forcing the island state to lurch back to the expensive fossil fuel era.

In December 2020, the arbitrator High Court Chief Justice Robert French found that the 2015 cable failure was not a force majeure event, as Basslink had claimed, but rather was caused by thermal overstressing arising from BPL’s operation of the interconnector.

In light of this finding, Justice French awarded the state and Hydro Tasmania in excess of $70 million, including costs related to the cable failure, and ordered Basslink to take actions to improve the operational performance and reliability of the cable.

The parties then came to a Standstill Agreement, allowing negotiations to take place to satisfy BPL’s obligations under the arbitration outcomes and allowing for BPL to try to refinance its debt.

But in late 2021, Barnett’s department wrote to Keppel Infrastructure Trust to advise that the state and Hydro Tasmania would not be extending the agreement, forcing Basslink into voluntary administration a month later.

In its statement on Thursday, Hydro Tasmania said it remained willing to discuss a way to provide funding to Basslink during the receivership and help transition the asset to an alternative commercial model.

At the time of publication, Basslink had not yet replied to a request for comment, but in October of 2021 – when the Standstill Agreement was scrapped – it described Tasmania’s handling of the dispute as “deeply regrettable.”

At that time, Basslink said that it had “acted purposefully and with care to ensure that all stakeholders’ interests, including the state, Hydro Tasmania, lenders’ as well as KIT’s institutional and retail Unitholders” had been taken into account.

Basslink also claimed in October 2021 that an attempt at a “prior sale process did not conclude because all parties, including the state and Hydro Tasmania, unfortunately, could not come to a satisfactory agreement with the bidder.”

More details to come.


Get RenewEconomy in your inbox, every day. To sign up to our free daily newsletter, just click here.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

New renewables and batteries improve grid reliability outlook, but more needs to get built on time, AEMO says

Immediate threat to the reliability of Australia's main grid has been pushed back into the…

25 August 2026

Post-2030 contract design for new renewables takes shape as working group agrees on firming price caps

Work advances on the design for key post -2030 contracts for new renewables and firming…

24 August 2026

Hefty network fees discussed as state government reveals massive scale of data centre grid connection demands

Some of the date centre proposals being discussed for NSW are among the largest in…

24 August 2026

“A Trojan horse for communism!” More big batteries head for review as familiar long distance objectors pile in again

Two more big batteries head for independent review as familiar long distance objectors file the…

24 August 2026

Linking electricity and safeguards could make wind projects viable, and oblige gentailers to actually Do Something

Linking the electricity grid with the safeguards mechanism would send clear price signal for wind…

24 August 2026

Australia’s biggest data centre to require 4 substations, 2 power lines, some batteries and 4 days of diesel backup

The massive 800 MW data centre will need city-scale electrical infrastructure, and will install enough…

24 August 2026