Solar

Tailem Bend solar farm doubles in size with completion of stage two – battery to come

Published by

The second stage of what was one of South Australia’s first large-scale solar farms, Vena Energy’s Tailem Bend, has finally been completed, with the commissioning of an additional 87MW of solar – and a 41.5MW, one hour battery still to come.

EPC contractor UGL said on LinkedIn that the combined 610,000 panels of the two stages of Tailem Bend would now produce up to 180MW of power for the region, east of Adelaide.

“Tailem Bend has been a fantastic project to work on with our client Vena Energy,” said UGL’s Matt Stone on LinkedIn on Monday.

“The team has delivered a quality asset to the O&M team who will initially operate it and continue to deliver a high level of maintenance and performance,” Stone said.

According to a joint statement from Vena Energy and ElectraNet, the energisation of Tailem Bend 2 kicked off in February of this year, when it was marked as “an important milestone” ahead of the commissioning of the hybrid project.

However, it took until August for the first power to be injected into the grid, and until now for commissioning to be complete, highlighting the ongoing complications for many projects in getting to full production.

ElectraNet project manager Hasan Fayyaz said earlier this year the distribution company had undertaken augmentation works and modifications at the Tailem Bend and Coorong 1 substations, as part of efforts to connect the project to the grid.

“When completed, the Tailem Bend 2 Hybrid Project will have a combined capacity of 128.5 MW derived from the now energised 87 MW solar farm and the upcoming 41.5 MW Battery Energy Storage System,” Hasan said.

The 95MW Tailem Bend 1 solar farm – the second large scale PV project in South Australia – came into full operation in early 2019, after having to be pared down from its original 108MW capacity due to connection and system constraints.

It was then formally opened in May 2019 by owners Vena Energy and off-taker Snowy Hydro, which had secured a 22-year power purchase deal for Tailem Bend 1 through its retail subsidiary Lumo.

The Tailem Bend battery is expected to be fully operational later this year, when it will operate with the second stage solar farm as a hybrid project, presumably to help store solar at times of negative prices and avoid some of the forced economic shutdowns that have plagued stage one of the project.

 

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024