Synergy gets approval for second big battery, starts promoting Collie giant

Published by

The state government owned utility Synergy has won planning approval for a much larger second stage of its first big battery to be located at the site of its former gas-fired power station in Kwinana.

The first stage of the Kwinana battery – sized at 100MW with two hours storage (200MWh) – began operations last month, the first such installation on the state’s main grid.

The second stage of the battery, Kwinana 2, will be four times the size – at 200MW and four hours storage (800MWh). It will then be trumped by an even installation at Collie, sized at 500MW and four storage storage (2,000MWh).

A Synergy spokesperson said the Metro Outer Joint Development Assessment Panel (JDAP) had given planning approval on Monday (May 29) for its second Battery Energy Storage System in Kwinana (KBESS2).

The spokesperson said Synergy is currently engaging suppliers and securing long lead time items for the next stage of the project. Once finalised, Synergy plans for construction to start later this year.

Meanwhile, Synergy has also begun community information sessions about the proposed Collie Battery Energy Storage System (CBESS), which will be built in the town that hosts the last of the state-owned coal generators that are to be closed before the end of the decade.

The first community session was held last Wednesday (May 24), and was described as an opportunity to learn more about the proposed battery, what it does, and where it will be built.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024