Sun Brilliance gets approval for WA’s biggest solar plant

Published by

A 100MW solar power plant in Western Australia’s Wheatbelt region has taken a significant step towards realisation after getting approval from the Mid-West Wheatbelt Joint Development Assessment Panel.

While the project’s initial timeline has slipped a little, it now appears likely Australia’s first “merchant” utility scale solar array will go ahead, although it will be competing against a rival plant in Queensland being developed by UK-based Eco Energy.

Aerial photo of Nyngan solar farm in NSW, which is 102MW

Perth-based developer Sun Brilliance confirmed the news last Friday, noting that the $160 million project will be a significant source of Large Scale Generation Certificates (LGCs) in WA.

The Mid-West Wheatbelt Joint Development Assessment Panel approved the plan at a meeting on November 28, with adjoining landowner Ray Lehman, and Sun Brilliance’s Ray Wills and Dilawar Singh answering questions posed by the panel.

The development group placed some conditions on the PV power plant and the proposed accompanying visitor precinct. These conditions include: that the project is developed within two years of the approval grant; that the electrical substation is relocated to a site at least 200 meters away from the nearest home; and that a detailed transport management plan be developed accounting for the construction period.

The 100 MW power plant will be located outside the WA Wheatbelt town of Cunderdin, 158 km east of Perth, at a property owned by Sun Brilliance known as Creswick. The plan is for sheep grazing to continue on the property at the same level as today, with the sheep reducing the need for for grass and weeds to be regularly cut as a part of scheduled plant Operations and Maintenance (O&M).

An advantage of the Creswick location is that it lies 2 km north of a 132 kV Western Power transmission line. Sun Brilliance will develop the 132 kV/22kV substation required.

“We have been very pleased with the professionalism of Western Power in their consideration of our project needs, and with just a few small variations on milestones, still within the framework of our original timeline,” said Sun Brilliance director Ray Wills.

Wills sits on the board of regional WA utility Horizon Power.

Sun Brilliance Chairman and CEO Dilawar Singh said that construction on the project is set to begin in April 2017, with the installation to be completed by September.

At the time of completion, the 100 MW project will likely be Australia’s largest by electricity production, when the effect of the single axis tracking system is taken into account.

The project developer must now finalise debt and equity financing and is aiming for a 70/30 split.

Recent indications are that funding conditions for large scale solar in Australia have improved rapidly recently, partly as a result of ARENA’s large scale solar scheme. The Sun Brilliance WA project did not apply for an ARENA grant.

Sun Brilliance is unwilling to provide further details on the progress it is making with its financing efforts, nor to the project’s revenue stream.

While it has fallen slightly in recent weeks, Green Energy Markets figures reveal LGCs are currently trading in the high $80/MWh range. The 100 MW project is expected to create 200,000 LGCs annually.

WA utility Synergy has developed very few renewable energy projects of its own in recent years, preferring to purchase certificates on the spot market – generally from solar and wind projects in the eastern states. RenewEconomy understands that WA Energy Minister and Treasurer Mike Nahan has instructed Synergy, which is state owned, to purchase LGCs locally, to encourage renewable project development in the state.

If Synergy comes to a purchase agreement with Sun Brilliance for the 100 MW project, it would significantly reduce the developer’s risk, with the electricity generated to be traded on the WA spot market.

The solar project is expected to create 150 jobs during the construction phase, and eight to ten full-time jobs during operation.

Sun Brilliance would not provide any details as to EPC arrangements nor to component suppliers. However, in its public presentation on the project it is revealed that it is considering both multicrystalline and cadmium telluride modules (CdTe) – with First Solar the only manufacturer with sufficient manufacturing capacity to supply 100 MW of CdTe panels.

Interestingly, the Sun Brilliance presentation notes that the warranted life of the project is 30 years. The warranty period indicates that dual-glass modules, where the foil backsheet is replaced by a second sheet of glass, are currently being considered by the developers. Glass-foil modules, the industry standard today, are issued with 20-year warranties as common practice.

Recent Posts

FRV starts generating power from its biggest Australian solar farm, which will supply Microsoft data centres

Spanish owned FRV starts generating power to its biggest solar farm to date, which has…

26 November 2024

NSW gives planning approval for giant 2 GWh battery at site of state’s likely last coal generator

NSW government gives planning approval for another giant battery to be built at the site…

26 November 2024

South Australia wants to bring back mothballed diesel plants due to lack of demand side options

South Australia wants to bring back two mothballed diesel generators for the next two summers,…

26 November 2024

Engie signs new offtake deal for charging and discharging services from Victoria Big Battery

Updated: Engie signs its first Australian virtual energy storage offtake deal, giving it access to…

26 November 2024

CSIRO spin-off raises record amount to fund solar heat and power tech, get industry off gas

Concentrated solar thermal company spun out of CSIRO has launched promising to deliver zero emissions,…

26 November 2024

Extended outages of “always on” baseload power leaves coal states vulnerable to heatwave

Absence of more than 3 gigawatts of "always on" baseload fossil fuel generators, including at…

26 November 2024