Solar power tower goes up in Australian desert, ready to grow tomatoes

Published by

Construction of a world-leading, concentrated solar power (CSP) tower plant that will supply electricity heat and desalinated seawater to grow tomatoes in the Australian desert has reached a major milestone, with the erection of the 127 metre tower.

The company behind the custom-built Port Augusta plant, Aalborg CSP, with construction group John Holland, put the final tower sections in place this week, topping it with the 234-tonne central boiler, which will soon receive the reflected sun rays from more than 23,000 mirrors.

As you can see in the video below, this final task – understood to be involve the largest lifts to this height ever undertaken in Australia – required some “careful calculations”.

Aalborg’s Integrated Energy System will be the first large-scale CSP-based technology in the world to provide multiple energy streams – heating, fresh water and electricity – for horticultural activities; an innovative and sustainable approach dreamed up by Adelaide-based outfit Sundrop Farms.

The company originally used finance from the Clean Energy Finance Corporation to develop a prototype of its proprietary closed-loop farming system, in which is successfully grew tomatoes year-round, using only sunlight and seawater.

In December 2014, Sundrop secured $100 million of funding from leading global private equity investor KKR, allowing it to proceed with plans to expand the prototype into a 20-hectare facility, including the CSP tower plant.

Sundrop has also secured a 10-year exclusive contract with Coles for the supply of tomatoes, creating jobs for up to 175 people.

Aalborg’s custom-build CSP plant will heat the greenhouses in wintertime and on cold summer nights, provide fresh water by desalinating seawater drawn from the nearby Spencer Gulf (5km from the site) and run a steam turbine to produce electricity.

“This groundbreaking project proves a new platform to address major global energy challenges. The construction progresses well and we are looking forward to harvest the first sunrays in the second half of 2016” – says Svante Bundgaard, CEO of Aalborg CSP.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: solar tower

Recent Posts

State green-lights plan for Australia’s biggest wind farm, with 219 turbines and two big batteries

Plans to build what would be Australia's biggest wind farm in have cleared a major…

18 May 2026

Australia’s biggest solar farm enjoys less curtailment, but lower prices, as big battery starts commissioning

Owner of Australia's two biggest operating solar farms reports significant jump in revenue, helped by…

17 May 2026

“Remarkable milestone:” Bowen says home battery installations continue to surge, pass 400,000

Home battery installs continue to surge despite rebate changes, passing 400,000, and matching the storage…

16 May 2026

Coal pollution is significantly reducing the output of solar panels, major study finds

Study by University of Oxford and University College London finds that coal pollution is significantly…

16 May 2026

Turbine blade breaks, falls to ground at wind farm damaged by lightning strike in 2019

A wind turbine blade has broken and fallen to the ground at a wind farm…

15 May 2026

Construction starts at state’s first “end-to-end” hydrogen and ammonia production plant

Construction is underway at state's first hydrogen and ammonia production plant, that will help insulate…

15 May 2026