Solar power tower goes up in Australian desert, ready to grow tomatoes

Published by

Construction of a world-leading, concentrated solar power (CSP) tower plant that will supply electricity heat and desalinated seawater to grow tomatoes in the Australian desert has reached a major milestone, with the erection of the 127 metre tower.

The company behind the custom-built Port Augusta plant, Aalborg CSP, with construction group John Holland, put the final tower sections in place this week, topping it with the 234-tonne central boiler, which will soon receive the reflected sun rays from more than 23,000 mirrors.

As you can see in the video below, this final task – understood to be involve the largest lifts to this height ever undertaken in Australia – required some “careful calculations”.

Aalborg’s Integrated Energy System will be the first large-scale CSP-based technology in the world to provide multiple energy streams – heating, fresh water and electricity – for horticultural activities; an innovative and sustainable approach dreamed up by Adelaide-based outfit Sundrop Farms.

The company originally used finance from the Clean Energy Finance Corporation to develop a prototype of its proprietary closed-loop farming system, in which is successfully grew tomatoes year-round, using only sunlight and seawater.

In December 2014, Sundrop secured $100 million of funding from leading global private equity investor KKR, allowing it to proceed with plans to expand the prototype into a 20-hectare facility, including the CSP tower plant.

Sundrop has also secured a 10-year exclusive contract with Coles for the supply of tomatoes, creating jobs for up to 175 people.

Aalborg’s custom-build CSP plant will heat the greenhouses in wintertime and on cold summer nights, provide fresh water by desalinating seawater drawn from the nearby Spencer Gulf (5km from the site) and run a steam turbine to produce electricity.

“This groundbreaking project proves a new platform to address major global energy challenges. The construction progresses well and we are looking forward to harvest the first sunrays in the second half of 2016” – says Svante Bundgaard, CEO of Aalborg CSP.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: solar tower

Recent Posts

Amazon inks its first ever standalone battery tolling agreement – with a project in East Gippsland

Global web services giant signs its first ever standalone battery "tolling" agreement, globally, in a…

2 September 2026

“Bloody dangerous territory:” World on track to exceed 1.5°C warming

Earth is on track to exceed 1.5 degrees of warming within years, the United Nations…

2 September 2026

“Fully funded, fully contracted:” Construction team ready to go on state’s largest solar-battery hybrid

Frontier Energy says it has secured all major contracts to start construction later this month…

2 September 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

New CEOs at CS Energy, CER, Ark Energy and Western Power; new role and hire…

2 September 2026

Scrapping VNI-West will “guarantee a massive increase” in power bills, former energy minister warns

Scrapping VNI-West and other projects designed to support renewable energy will result in "massive" electricity…

2 September 2026

Fortescue green iron rival wins Arena cash to scale up Perth demonstration plant

Element Zero, the upstart Pilbara green iron contender and survivor of a legal challenge from…

2 September 2026