Solar

Solar project seeks federal green tick for its koala protection efforts after winning CIS tender

Published by

One of the winners of Australia’s largest renewable energy tenders is still wading through the EPBC, as it tries to convince federal bureaucrats it is doing enough to protect koalas.

The public has another chance to comment on the 250 megawatt (MW) Hopeland solar project until February 10, as part of the federal assessment stream it’s going through. 

The slightly more complicated assessment process came about because the federal Department of Climate Change, Energy, the Environment and Water (DCCEEW) wants more information about how the developers will mitigate potential damage to threatened flora and fauna. 

Developer Pacific Partnerships originally identified 10 threatened or endangered species as potentially living in the area – the painted honeyeater, white-throated needletail, fork-tailed swift, koala, grey-headed flying fox, grey snake, yakka skink, Dunmall’s snake, Brigalow woodland snail, and Corben’s long-eared bat.

Now the focus is squarely on looking after koalas.

Documents accompanying the invitation for public comment outline plans for a 100m-wide koala corridor, koala-proof fencing to stop them from getting in among the solar panels, a dam-turned -waterhole, and a koala offset area 45km to the south. 

Pacific Partnerships says it will now be possible to avoid most of the remnant eucalypt open forest and all of the endangered Brigalow scrub, and disturbing a maximum of 62 per cent of the land area

The problematic part is the project requires significant tree clearing, even though the land itself is in a heavily farmed area, and the focus is very much on koalas.

Pacific Partnerships will need to clear 140.3 hectares of koala habitat that could house koalas and grey-headed flying-foxes.

That’s about 40 per cent of the remnant and regrowth eucalypts on the site. Other patches of vegetation such as brigalow, acacias, and sparsely growing eucalypts will also need to be felled.

Battery is on the way

The southern Queensland project will also come with a 175 MW, two hour battery and which is pitched as a partial replacement for the nearby Kogan Creek coal-fired power station.

The developer has left the door open to expanding that battery up to 250 MW and 500 megawatt hours (MWh), after securing a connection agreement from the Australian Energy Market Operator (AEMO) for the battery component a month ago, it said on LinkedIn.

The journey to construction is proving to be a longer route out of the planning process than usual for a solar-battery project, thanks to the more intense EPBC pathway. 

The project locked in development approval three years ago, and a connection approval in April 2024 to hook into the grid via Powerlink’s neighbouring 275kV Western Downs substation.

But even if federal DCCEEW is giving the project closer scrutiny, it has the backing of other parts of the federal government. 

In December 2024, Hopeland solar was one of 19 wind, solar and hybrid projects to win what was at the time Australia’s largest ever renewable energy tender with 6.4 gigawatts of projects awarded.

The Hopeland project is one of construction group CIMIC’s initial forays into renewable energy.
It bought the project via its in-house developer Pacific Partnerships from Brisbane-based Renewable Energy Partners in August 2023, and says the battery element is its third large-scale renewable asset to gain a connection agreement.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

AEMO review rejects radical change of governance, green lights auction house exit

AEMO should retain its control over long term planning but get rid of investment-driven ASL,…

10 August 2026

Factories and farms will deliver the next solar boom, but look out for cowboys – and please add batteries

Nearly a week after federal Labor announced plans to expand the SRES, industry is still…

10 August 2026

Australian lithium refining pilot gets government funding for “cleanest and most cost efficient” technology

Australian lithium refining technology that says it can be powered by renewables and uses no…

10 August 2026

State owned utility accused of hiding safety issues at troubled coal generator from JV partner

State owned utility faces $1 billion lawsuit, accused of withholding incidents, safety warnings at troubled…

10 August 2026

Don’t let the data centre gold rush become an excuse to pollute

National rules should ensure new data centres bring new clean power with them, rather than…

10 August 2026

Independent panel approves Sydney big battery sent for review by objectors from tiny towns 800 km away

Major battery proposed for centre of Sydney gets development approval from independent panel, after being…

10 August 2026