The Western Australian government has praised the use of solar and batteries to provide power to remote households and businesses, after Western Power replaced costly 230km of costly grid connections with stand-alone power systems that slashed costs and improved reliability.

The deployment of 52 stand alone power systems by Western Power has now been completed, enabling it to avoid the costly replacement of around 230 kilometres of overhead powerlines.

The stand-alone power systems (SAPS) combined various amounts of solar, battery storage and a back-up diesel generator, all depending on the customer needs and consumption, and was spread across dozens of homes in Western Australia’s Mid-West region (north of Perth), the Goldfields, the eastern Wheatbelt and Great Southern regions.

In remote areas, maintaining a connection to the main grid can require kilometres of vulnerable poles and wires, that are comparatively expensive to maintain, and can leave homes and businesses without power for days at a time if the lines are damaged.

The falling costs of solar power and battery storage now mean it can be cost effective to replace expensive poles and wires with onsite solar and storage. Networks in the eastern states, particularly in NSW, are being encouraged to do the same under new rules that allow the practice, and new industry incentives that will penalise networks for not maintaining power.

The removal of the powerlines will also improve land amenity for farmers whose land they had passed through, as well as reducing the risk of bushfires triggered by falling lines.

The roll out of 52 SAPS followed an initial trial undertaken by Western Power that saw an initial group of six households receive stand-alone power systems in 2016. The trial exceeded expectations, with more than 200 hours of power interruptions avoided over the course of a three-year trial.

In Wansbrough, Western Power will also trial the use of a microgrid, with two premises served by a single stand alone power system, allowing power to be shared between the two premises without needing to be connected to WA’s main grid.

“Stand-alone power systems are a cost-effective and innovative approach to providing power to WA’s regional customers,” Western Australian energy minister Bill Johnston said.

“Using SAPS is part of the McGowan Government’s commitment to providing reliable and safe power to our customers that are on the fringe of the grid.

“We have made significant headway in transitioning towards a low carbon future with the recent release of the Whole of System Plan, DER Roadmap, the big battery and commissioning of SPS technology,” Johnston added.

Following earlier trials conducted by Western Power, the Western Australian government amended relevant legislation to allow households and businesses to be served by stand alone power systems when more cost effective than maintaining grid connections.

The successful roll out of stand-alone power systems could lead to a much wider roll out, with Western Power having previously identified around 15,000 customers that could benefit by being taken off-grid.

 

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024