Solar costs down another 14% in Brazil energy auction, as 1GW awarded

Published by

Brazil is set to add 53 new large-scale solar and wind farms to its national power generation mix, after the government awarded contracts for the development of 1.5 gigawatts of new renewable capacity in its latest energy auction.

The auction’s success – which will deliver nearly 1GW (929.3MW) of solar capacity and just over half a gigawatt (548.2MW) of wind energy – has been partly attributed to the government’s decision to raise a price cap to attract bidders.

Bloomberg reports that global solar companies including SunEdison and Rio Alto Energia were among those who bid and won contracts at the “hugely competitive” auction, which follows on from the 800MW solar only auction the South American nation held in August.

In August, the projects were awarded at an average price of around $US0.0842/kWh — which was around 13.5% below the maximum price set for the auction. This time around, solar generation was priced at an average of $US77.49 a megawatt-hour ($US0.0774/kWh), which was also below the ceiling price.

“Solar prices were a nice surprise,” said Igor Walter, a director at the Ministry of Mines and Energy, quoted in Bloomberg. “The prices are realistic. The ceiling price raise was determined to bring competitiveness to the auction and generate competition.”

A similar result was achieved last month in Chile, which awarded five global wind and solar companies 20-year contracts to supply 1,200GWh to the Chilean electricity market from 2017.

The five companies – including Abengoa, Aela Generacion, Ibereolica Cabo Leones, Amunche Solar SpA (a subsidiary of Spanish Solarpack) and First Solar (via SCB II) – offered an average bid price of $US79.3/MWh, the lowest average price per MWh for a local energy auction since 2007.

Both these results augur well for Central American neighbour, Mexico, which is planning its first-ever energy auction to award contracts priced in US dollars, in an effort to attract more international developers to the country’s newly opened power industry.

Further north, in the US state of Texas, the Austin City Council received some of the cheapest bids for solar power ever recorded in its solar auction of September, attracting more than 600MW of bids at under five US cents per kWh.

Back in Brazil, initial deliveries of the newly contracted solar and wind developments are scheduled for November 2018. The government estimates those projects will cost companies some 6.8 billion reais ($US1.77 billion).

On solar alone, Brazil has set an ambitious goal of having 7GW of installed capacity by 2024, according to Mauricio Tolmasquim, the head of Brazil’s Energy Research Agency, known as EPE. That’s an increase from last year when the government was targeting 3.5 gigawatts of solar capacity in operation by 2023.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Energy Insiders Podcast: Getting the best out of the grid

Energy expert Gabrielle Kuiper on getting the best out of distributed energy resources in the…

29 November 2024

Australian homes could slash energy bills by two thirds by cutting out gas and petrol, AEMC says

Australian households could lower their bills by over two thirds if they fully electrify their…

29 November 2024

In the end, the only blackouts were in the media headlines: But there has to be a better way to do this

Blackout featured prominently in media headlines this week, but not on the grid. But as…

29 November 2024

Trina submits approval for Victoria big battery, as locals campaign against solar and storage projects

Trinasolar and Mint Renewables have now both lodged planning applications for neighbouring big batteries in…

29 November 2024

Australia to reshape manufacturing base as Greens deal excludes fossil fuels from flagship industry policy

Greens make last minute commitment to vote for $22 billion Future Made in Australia policy…

29 November 2024

Andrew Forrest seeks green tick for another wind and battery project as Clarke Creek powers up

Andrew Forrest's Squadron Energy seeks green tick for new wind and battery project in NSW…

29 November 2024